Bitdeer Technologies: Investor Profile of the Bitcoin Miner Turning to AI Cloud

Bitdeer Technologies mines bitcoin with its own SEALMINER machines and is turning power sites into AI data centres. Its sites, latest numbers, $1.95bn of borrowings, main risks and the dates ahead.

Rows of long grey mining halls with banks of cooling fans along their sides at Bitdeer's Tydal data centre in Norway, with green hills and mountains behind.
Photo: Bitdeer

Bitdeer Technologies mines bitcoin with SEALMINER machines it develops itself. It is also converting part of its 3.1 gigawatts of power capacity into data centres for AI customers. That shift brings a $2.9bn order backlog, but also heavy spending, rising debt and a widening loss.

What Bitdeer does

Bitdeer is headquartered in Singapore and has data centres in the United States, Norway, Bhutan, Ethiopia and Malaysia. Its shares trade on Nasdaq under the ticker BTDR. It switched its accounts from IFRS to US GAAP from 1 January 2026.

It earns money in three main ways:

  • Self-mining, where it mines bitcoin for its own account. This brought in $217.5m of the $320.7m of third-quarter revenue.
  • Hosting and co-mining, where it runs machines for, or shares output with, other parties.
  • AI cloud, where it rents out computing capacity built on graphics processors and leases data centre space to AI companies.

The SEALMINER machines are Bitdeer's own product. Since the second quarter of 2026 it has kept them for its own fleet rather than selling them, and external SEALMINER sales fell to $0.3m in the third quarter from $11.4m a year earlier.

Bitdeer Technologies: share price, chart and news

An aisle between rows of black mesh-door server cabinets, keys in their locks, inside Bitdeer's Southeast Asia data centre.
An aisle between rows of black mesh-door server cabinets, keys in their locks, inside Bitdeer's Southeast Asia data centre. Photo: Bitdeer

The sites and the AI build-out

At 31 October Bitdeer reported 3,121.0 MW of electrical capacity: 1,747.7 MW online and 1,373.3 MW in the pipeline.

SiteCapacityUse and timing
Rockdale, Texas563 MW onlineMining; under evaluation for AI; 179 MW expansion energising from Q4 2026
Jigmeling, Bhutan500 MW onlineMining
Massillon, Ohio221 MW onlineMining
Gedu, Bhutan100 MW onlineMining
Molde, Norway84 MW onlineMining; AI conversion at an early stage
Oromia, Ethiopia50 MW onlineMining
Tydal, Norway60.5 + 60.5 MW, then 42.7 IT MWAI lease; Q4 2026, Q1 2027 and H2 2027
Clarington, Ohio570 MWTiming to be updated; legal proceedings may affect it
Weathersfield, Ohio300 MWQ4 2028
Fox Creek, Alberta101 MWQ4 2027
Knoxville, Tennessee55 MWQ4 2027, after equipment delays

The company has also bought about 200 acres next to Rockdale for AI and high-performance computing.

The mining fleet is large and getting more efficient. At the end of September Bitdeer's self-mining hashrate was 82.3 EH/s, with a further 28.7 EH/s under co-mining arrangements. The fleet averaged 15.4 joules per terahash in the third quarter, against 20.1 a year earlier, and used 3.1 terawatt-hours of electricity at an average cost of $47 per megawatt-hour.

The AI cloud business

In September Bitdeer had 4,328 GPUs deployed, running at 95% utilisation, with annual recurring revenue of about $86m. Its Bitdeer AI unit also announced a collaboration with NVIDIA on safety controls for enterprise AI agents. AI cloud revenue reached $20.4m in the third quarter, against $1.8m a year earlier.

The backlog jumped to about $2.9bn by September from $0.9bn in August. The largest contract is a 16-year lease of the Tydal campus to Volta, worth about $4.7bn over the base term and about $8.0bn with a one-time eight-year extension; the tenant can leave without a fee after ten years. In Malaysia, Bitdeer lists six AI cloud sites, one of them already online, including a 9.5MW Cyberjaya site with all GPU capacity contracted for more than $800m over five years.

Bitdeer has also said it will move its infrastructure updates from monthly to quarterly, published with its results.

The latest numbers

Q3 2026Q3 2025
Revenue$320.7m$169.7m
AI cloud revenue$20.4m$1.8m
Gross profit$10.8m$39.7m
Net loss$125.5m$30.1m
Adjusted EBITDA$69.6m$25.5m
Bitcoin mined3,8551,109

Against the second quarter, revenue rose 40% from $228.8m, adjusted EBITDA more than doubled from $31.1m and the gross result swung from a loss of $8.5m to a small profit. The net loss still included a $54.6m non-cash charge on a loan denominated in digital assets.

Over the first nine months of 2026, revenue was $738.5m, the gross loss $36.7m and the net loss $377.3m. Operating activities used about $499.5m of cash. Third-quarter capital spending of $478m split into about $110m for SEALMINER production and about $368m for data centres and GPU equipment.

Balance sheet at 30 September

  • $213.7m cash, including restricted cash
  • $1.95bn total borrowings
  • 276.2m shares: 231.8m Class A and 44.4m Class V

Total liabilities were about $2.82bn against total assets of $3.86bn, leaving $1.04bn of equity. The company held only 47 bitcoin at the end of September, against 2,029 a year earlier, so it has little in reserve to sell.

The main risks

Financing. Chief financial officer Michael Potter named completing financings as one of three priorities. Unrestricted cash fell to $163.7m from $456.8m in three months, according to Earnings Whispers, and the build-out still needs large sums.

Dilution. Bitdeer sold shares through an at-the-market programme in the quarter, raising a net $58.0m, and raised a net $363.6m from convertible notes earlier in the year.

Related-party debt. About $738.6m of borrowings come from a related party, including borrowings denominated in bitcoin, whose value swings caused a $54.6m non-cash loss in the quarter.

Bitcoin and power. Mining income moves with the bitcoin price and network difficulty, and average power costs rose to $47 per megawatt-hour.

Delivery. Several sites have slipped, including Knoxville and Fox Creek, and legal proceedings may affect the timing at Clarington. The Tydal tenant can walk away after ten years.

What to watch next

Dates and milestones

  • Q4 2026: Tydal phase 1 (60.5MW) and the first energisation of the 179 MW Rockdale expansion.
  • Q1 2027: Tydal phase 2 and the 9.5MW Cyberjaya AI site in Malaysia.
  • Q2 2027: the 67MW and 21.7MW Malaysian AI sites, the second targeted to go live in April 2027.
  • Fourth-quarter results, when management plans to give 2027 guidance and AI cloud margin targets; no date published yet.
  • The project financings for Tydal and Malaysia.

Sources

Related stories

Markets

Bitdeer Technologies Posts Record $320.7m Revenue as Its Net Loss Widens to $125.5m

Bitdeer Technologies lifted quarterly revenue 89% to $320.7m as it mined 3,855 bitcoin, but its net loss quadrupled to $125.5m and unrestricted cash fell to $163.7m after heavy…

Investing

HIVE Digital Technologies: An Investor Profile of the Bitcoin Miner Building an AI Cloud

HIVE Digital Technologies mines bitcoin, mainly in Paraguay, while building an AI GPU cloud in Canada. Its assets, latest numbers, debt, dilution, risks and the dates that matter…

Investing

D-Wave Quantum: Investor Profile of the Annealing Pioneer Building a Gate-Model Machine

D-Wave Quantum sells quantum computing through the cloud, on-site systems and services. It holds $503m of cash and securities and a growing order book, but its losses keep rising.

Investing

Dave Investor Profile: ExtraCash, 31% Growth and a Justice Department Lawsuit

Dave is a Los Angeles neobank built on ExtraCash advances. Its latest results, $315m of cash and investments, 12.8m shares, the DOJ lawsuit, credit risks and what to watch next.

Investing

Aya Gold & Silver Corrects Q3 Cash Costs to $14.28 an Ounce After Silver Double Count

Aya Gold & Silver refiled its Q3 MD&A after silver in transit was deducted twice. Zgounder ounces sold rise to 1,392,478 and cash costs fall to $14.28 from $15.51. Revenue and…

Investing

FDA Rejects Summit's Lung Cancer Drug Ivonescimab Over Phase 3 Survival Miss

The FDA has rejected Summit Therapeutics' lung cancer drug ivonescimab, saying slower tumour growth in the phase 3 HARMONi trial was not enough without a clear gain in survival.

Investing

Red Cat Withdraws Its $150m to $180m 2026 Revenue Target After $11.8m Third Quarter

Red Cat Holdings has withdrawn its $150m to $180m revenue target for 2026 after third-quarter sales of $11.8m, blaming slower defence funding. Its quarterly net loss more than…

Investing

Berkshire Reveals $689m Bending Spoons Stake, Doubles Lennar and Trims Bank of America Again

Berkshire Hathaway's third-quarter 13F shows a new Bending Spoons stake worth $689m, a doubled Lennar holding and 27.5 million more Bank of America shares sold, while Apple stayed…