Cipher Digital, until recently a bitcoin miner called Cipher Mining, is turning its Texas power sites into data centres for artificial intelligence and other high-performance computing. It has signed long leases with large tenants and borrowed heavily to build them, so the next two years depend on delivering on time.
What Cipher Digital does
Cipher describes itself as a developer and operator of industrial-scale data centres for high-performance computing (HPC) hosting, alongside bitcoin mining. Its strategy is to secure large blocks of grid power, build the buildings and electrical systems, and lease the space to hyperscale cloud companies and AI developers on terms of 10 to 20 years.
Bitcoin mining still produced most of its revenue in the third quarter of 2026, but the mix is changing fast. Its Black Pearl site stopped mining in February 2026 and started earning rent in August. The company's sites are concentrated in Texas.
Cipher Digital: share price, chart and news

The sites
| Site | Size | Status | Tenant |
|---|---|---|---|
| Black Pearl, Wink, Texas | about 300MW | first phase delivered August 2026, more halls due by year-end | investment-grade hyperscaler, 15 years |
| Barber Lake | 300MW | phased delivery from Q4 2026 to Q1 2027 | Fluidstack for 10 years, then an unnamed AI lab for 10 |
| Stingray | 100MW | building shell due in Q4 2026, lease start expected in 2027 | not named |
| Odessa | 207MW | bitcoin mining on fixed-price power from Luminant | own use |
| Colchis | potential 1GW | conditional ERCOT base-load classification | none yet |
| Horizon, Texas | 70MW | acquired, power expected in 2029 | none yet |
In March 2026 Cipher also signed a 15-year lease with an investment-grade hyperscale tenant, with phased delivery expected to begin in 2027, according to its quarterly filing, which does not say which site it covers. It says another 270MW could be available in 2027, with tenant talks and design work under way, and it counts a total development pipeline of about 5.9 gigawatts. Pipeline megawatts are plans, not working capacity, and each new site will need a tenant, financing and a grid connection before it earns rent.
Google has agreed to support certain Fluidstack lease payments at Barber Lake if specified events occur. The second 10-year term at that site, signed with the AI lab, adds about $5.2bn of rent and takes contracted revenue there to about $9.1bn.
Latest numbers, cash and debt
Third quarter 2026
- $26.7m revenue, of which $5.9m from HPC leasing
- $10.0m adjusted EBITDA loss, against a $40.8m profit a year earlier
- $5.45bn long-term borrowings at 30 September
Third-quarter revenue fell 63% from $71.7m a year earlier as mining revenue dropped to $20.8m. The operating loss widened to $71.9m. A $127.2m non-cash gain on its warrant liability produced net income of $31.6m, but on a diluted basis the company lost 22 cents a share. For the first nine months of 2026 revenue was $86.4m and the net loss $350.2m. Operating activities used $283.2m of cash over the same period.
The company held about 310 bitcoin at 30 September, worth $25.9m, down from about 1,433 at the end of 2025.
Cipher ended September with $656.0m of cash and equivalents and $2.2bn of restricted cash, most of it raised through secured notes and reserved for construction and debt service. Management says its resources cover at least the next 12 months.
Its borrowings include $1.3bn of zero-coupon convertible notes due 2031, senior secured notes issued for its Cipher Compute, Black Pearl and Stingray projects, and a $200m revolving credit facility from Morgan Stanley. On 16 October it added $850m of zero-coupon convertible notes due 2032, with capped calls lifting the effective conversion price to $28.35. In the same month about $165.9m of 1.75% notes due 2030 were exchanged for roughly 40.7m shares.
Shareholders' equity was $600m at 30 September against total liabilities of $7.04bn. The share count was 456.4m on 30 October, up from 405.0m at the end of 2025. The company raised $129.2m by selling shares on the market in the first nine months, and a warrant liability of $504.9m will keep swinging reported profits.
Main risks
What could go wrong
- Construction and cost: Cipher spent $2.52bn on property and equipment in nine months; at Barber Lake it absorbs the first $359.3m of cost overruns above budget.
- Tenant concentration: a handful of tenants, including Fluidstack, account for its contracted rent, and tenant guarantees take effect only after rent starts and are subject to limits such as caps.
- Debt and dilution: more than $5bn of long-term debt, convertible notes and share sales could dilute holders.
- Power and weather: its sites are concentrated in Texas, exposing it to ERCOT rule changes, power costs and storms.
- Bitcoin price: remaining mining revenue and its bitcoin holdings move with the market.
The Colchis classification and the gas pipelines are conditional or early-stage. The contracted $9.1bn at Barber Lake is earned only as space is delivered over 20 years.
What to watch
| When | What |
|---|---|
| By end of 2026 | Remaining Black Pearl data halls come online |
| Q4 2026 | Stingray building shell completed |
| Q4 2026 to Q1 2027 | Phased handover of Barber Lake to Fluidstack |
| 2027 | Stingray commencement; delivery under the March 2026 hyperscaler lease begins; up to 270MW more capacity |
| 2029 | Horizon site expected to be energised |
The fourth-quarter report will show how much HPC rent replaces lost mining revenue. Investors will also watch for any new tenant for Colchis, for how the company funds its remaining build costs, and for whether further convertible notes or share sales follow the October issue.
Sources
- Cipher Digital via GlobeNewswire (Finviz): Cipher Digital Provides Third Quarter 2026 Business Update
- US SEC (EDGAR): Cipher Digital Inc. Form 10-Q for the quarter ended 30 September 2026
- InvestorsHub (Finviz): Cipher Digital reports $27 million in Q3 revenue as HPC leasing begins and contracted revenue reaches $9.1 billion at Barber Lake
- Cipher Digital: Cipher Digital company website