Montage Gold has poured its first gold at the Koné mine in Côte d'Ivoire, months ahead of its original target of the second quarter of 2027. The company says the build is on budget and expects the mine's oxide circuit to reach commercial production by the end of this year.
First bar from Koné
Montage (TSX: MAU, OTCQX: MAUTF) said the first pour took place on 26 September and produced about 1,140 ounces of gold. Ore first went into the plant's oxide circuit on 8 September, and more than 400,000 tonnes had been processed by the time of the announcement on 27 September.
Construction started in December 2024. Montage added a separate oxide circuit, which handles the softer weathered ore near surface, and finished it early. That let the company start producing before the main hard-rock crushing and grinding circuit is complete. The hard-rock circuit remains on budget and on schedule for the second quarter of 2027, the company said.
Chief executive Martino De Ciccio said the operation adds to the country's list of producers. "Koné is now the ninth operating gold mine in Côte d'Ivoire," he said.
The shares closed at C$19.90 on Friday 25 September, the last session before the announcement, giving a market value of about C$8.1bn, according to Stockwatch data.
Montage Gold: share price, chart and news
What the mine is built to do
Koné is Montage's flagship. Its 2024 updated feasibility study set out a 16-year mine life, with more than 300,000 ounces a year over the first eight years. Probable reserves in that study were 4.01 million ounces at 0.72 g/t gold, split between the Koné deposit and the smaller, higher-grade Gbongogo Main deposit.
Koné at first gold
- 1,140 oz gold in the first pour on 26 September
- 4.01 Moz Probable reserves at 0.72 g/t in the 2024 study
- 6.29 Moz Measured and Indicated resources after the June 2026 update
The resource has grown since that study. In June, Montage reported Measured and Indicated resources of 6.29 million ounces at 0.80 g/t across the mine, with Inferred resources of 2.03 million ounces at 0.68 g/t. Higher-grade satellite deposits now hold 1.66 million Measured and Indicated ounces at 1.51 g/t. The company has outlined 12 deposits and hit gold at 25 targets, and is drilling more than 130,000 metres at Koné this year.

Next steps at Koné
President and chief development officer Peder Olsen said doing much of the construction work itself cut capital costs and shortened the timeline. The early ore is coming from the Koné deposit and going straight into the mill, which keeps rehandling and working capital low.
Montage plans to start mining Gbongogo Main late in the fourth quarter of 2026, with other satellite deposits to follow during 2027. It also plans an updated life-of-mine plan with year-end 2026 reserves and resources. That plan should take in the newer deposits, the oxide circuit and the switch to owner-operated mining.
Key dates
- Q4 2026: oxide circuit ramp-up to commercial production.
- Late Q4 2026: first mining at Gbongogo Main.
- Q2 2027: completion of the hard-rock comminution circuit.
- With year-end 2026 reserves: updated life-of-mine plan.
Construction has created about 3,600 jobs, more than 95% held by Ivorian nationals, and the operation is expected to employ about 1,500 people permanently.
Risks that remain
A first pour is the start of a ramp-up, not proof of steady output. The plant still has to show it can run at design rates and recoveries. The hard-rock circuit, which handles most of the ore over the mine's life, is still being built. Montage has funded the build partly with debt and a gold stream from Wheaton Precious Metals, so lenders and the stream holder have first claims on part of the cash flow. The reserve grade is low at 0.72 g/t, which leaves profits sensitive to costs and the gold price. Montage's own filings also flag risks around permits, power availability and title in Côte d'Ivoire.