Montage Gold Pours First Gold at Koné in Côte d'Ivoire, Months Ahead of Schedule

Montage Gold poured about 1,140 ounces at its Koné mine in Côte d'Ivoire on 26 September, well before its Q2 2027 target, and expects commercial production on the oxide circuit in the fourth quarter.

A yellow excavator loads a yellow haul truck with red earth at a Montage Gold mine site.
Photo: Montage Gold

Montage Gold has poured its first gold at the Koné mine in Côte d'Ivoire, months ahead of its original target of the second quarter of 2027. The company says the build is on budget and expects the mine's oxide circuit to reach commercial production by the end of this year.

First bar from Koné

Montage (TSX: MAU, OTCQX: MAUTF) said the first pour took place on 26 September and produced about 1,140 ounces of gold. Ore first went into the plant's oxide circuit on 8 September, and more than 400,000 tonnes had been processed by the time of the announcement on 27 September.

Construction started in December 2024. Montage added a separate oxide circuit, which handles the softer weathered ore near surface, and finished it early. That let the company start producing before the main hard-rock crushing and grinding circuit is complete. The hard-rock circuit remains on budget and on schedule for the second quarter of 2027, the company said.

Chief executive Martino De Ciccio said the operation adds to the country's list of producers. "Koné is now the ninth operating gold mine in Côte d'Ivoire," he said.

The shares closed at C$19.90 on Friday 25 September, the last session before the announcement, giving a market value of about C$8.1bn, according to Stockwatch data.

Montage Gold: share price, chart and news

What the mine is built to do

Koné is Montage's flagship. Its 2024 updated feasibility study set out a 16-year mine life, with more than 300,000 ounces a year over the first eight years. Probable reserves in that study were 4.01 million ounces at 0.72 g/t gold, split between the Koné deposit and the smaller, higher-grade Gbongogo Main deposit.

Koné at first gold

  • 1,140 oz gold in the first pour on 26 September
  • 4.01 Moz Probable reserves at 0.72 g/t in the 2024 study
  • 6.29 Moz Measured and Indicated resources after the June 2026 update

The resource has grown since that study. In June, Montage reported Measured and Indicated resources of 6.29 million ounces at 0.80 g/t across the mine, with Inferred resources of 2.03 million ounces at 0.68 g/t. Higher-grade satellite deposits now hold 1.66 million Measured and Indicated ounces at 1.51 g/t. The company has outlined 12 deposits and hit gold at 25 targets, and is drilling more than 130,000 metres at Koné this year.

Gold over the last three months. Exchange data, delayed up to 15 minutes.
Gold over the last three months. Exchange data, delayed up to 15 minutes.

Next steps at Koné

President and chief development officer Peder Olsen said doing much of the construction work itself cut capital costs and shortened the timeline. The early ore is coming from the Koné deposit and going straight into the mill, which keeps rehandling and working capital low.

Montage plans to start mining Gbongogo Main late in the fourth quarter of 2026, with other satellite deposits to follow during 2027. It also plans an updated life-of-mine plan with year-end 2026 reserves and resources. That plan should take in the newer deposits, the oxide circuit and the switch to owner-operated mining.

Key dates

  • Q4 2026: oxide circuit ramp-up to commercial production.
  • Late Q4 2026: first mining at Gbongogo Main.
  • Q2 2027: completion of the hard-rock comminution circuit.
  • With year-end 2026 reserves: updated life-of-mine plan.

Construction has created about 3,600 jobs, more than 95% held by Ivorian nationals, and the operation is expected to employ about 1,500 people permanently.

Risks that remain

A first pour is the start of a ramp-up, not proof of steady output. The plant still has to show it can run at design rates and recoveries. The hard-rock circuit, which handles most of the ore over the mine's life, is still being built. Montage has funded the build partly with debt and a gold stream from Wheaton Precious Metals, so lenders and the stream holder have first claims on part of the cash flow. The reserve grade is low at 0.72 g/t, which leaves profits sensitive to costs and the gold price. Montage's own filings also flag risks around permits, power availability and title in Côte d'Ivoire.

Sources

Related stories

Investing

Montage Gold: From Developer to Producer as Koné Ramps Up in Côte d'Ivoire

Montage Gold poured first gold at Koné in September and produced 23,462 ounces in October. It holds US$205.6m of liquidity, but the hard-rock circuit is not due until Q2 2027.

Investing

SSR Mining Bids C$6.75 a Share for Nevada Gold Developer Roxmore

SSR Mining will pay C$6.75 a share in cash plus SpinCo shares for Roxmore Resources, valuing it at about US$464m, to add the 5.2 million-ounce Converse gold project next to its…

Business

Thesis Gold & Silver Files Its Lawyers-Ranch Project Description With BC Regulators

Thesis Gold & Silver has sent the Detailed Project Description for its Lawyers-Ranch gold-silver project to BC's Environmental Assessment Office, setting up the Readiness Decision…

Business

Banyan Gold Closes a C$54.3m Share Sale as Franco-Nevada Buys 10 Million Shares

Banyan Gold has closed a C$54.3m placement at C$2.00 a share, with Franco-Nevada taking 10 million shares, to fund drilling, engineering and permitting at its AurMac project in…

Business

Québecor Makes a C$31bn Cash-and-Share Bid for Telus, Which Warns of Regulatory Risk

Québecor has offered C$6.35 in cash plus 0.17 of its own shares for each Telus share, a bid worth about C$31bn. The Telus board says the price falls short and the regulatory risk…

Business

Tyson Foods Shares Jump 8.7% as Beef Outlook Outweighs a $74m Quarterly Loss

Tyson Foods posted a $74m fourth-quarter net loss and adjusted EPS of $0.61, down 47%, yet its shares closed 8.7% higher on Monday as its 2027 beef outlook pointed to far smaller…

Business

Roche Wins FDA Approval for Breast Cancer Pill Wilserdly After 62% Cut in Progression Risk

The FDA approved Roche's all-pill Wilserdly combination for ESR1-mutated advanced breast cancer after it cut the risk of progression or death by 62%. A ruling on early-stage use is…

Business

ULA Loses Its First Mission as Vulcan Rocket Fails With 40 Amazon Leo Satellites on Board

United Launch Alliance's Vulcan rocket failed about 10 minutes after lift-off on Sunday, and all 40 Amazon Leo satellites were lost. Amazon fell 3.3% on Monday as space stocks…