Pulsar Helium has told investors it intends to fund most of its planned helium and carbon dioxide plant in Minnesota with project debt and public-sector loans, topped up from its own cash, and to keep new share issues to a minimum. No lender or agency has committed any money yet.
The plant Pulsar wants to build
The plan, published on 12 October 2026, follows Pulsar's acceptance on 1 October of a binding proposal from Chart Energy & Chemicals, a subsidiary of Baker Hughes since that group bought Chart Industries in July. Chart would supply equipment for a helium purification and liquefaction plant and a carbon dioxide plant, which Pulsar calls its Rare Gas Hub.
The helium unit has a nameplate capacity of 861 litres of liquid helium an hour, which Pulsar equates to about 7.5 million litres a year if it ran continuously at that rate. The CO2 unit is sized for 300 tonnes a day, or about 109,500 tonnes a year on the same basis. Design purities are 99.999% for helium and 99.99% for CO2. Storage and loading equipment for CO2 sits outside Chart's scope.
Chart equipment proposal
- US$85.5m total equipment price, paid in stages
- 861 litres an hour of liquid helium at nameplate capacity
- 300 tonnes a day of CO2 processing capacity
Pulsar Helium: share price, chart and news

How the payments work
The US$85.5 million is an equipment price only. It excludes taxes and tariffs, installation, commissioning, site works and other owner costs, so the total installed cost will be higher. Pulsar has not yet published that figure.
A first payment of about US$5.0 million is due on signing and approval by the TSX Venture Exchange, and Pulsar said it would come from cash. It includes US$750,000 owed under an existing limited notice to proceed. The second payment, US$8.55 million, is scheduled for 31 January 2027 and would let Chart start ordering long-lead items. Pulsar said this payment depends on further funding.
If that January payment is missed, the project moves into a suspension period of up to 180 days during which the reserved liquefaction equipment stays protected for Pulsar, and no cancellation charge arises from the suspension alone. Should Pulsar later cancel for convenience, the charge rises with the work done, up to 70% of the contract value. Manufacturing is expected to take about two years after the second payment, although some liquefaction equipment has already been built.
Debt first, equity last
Chief executive Thomas Abraham-James said the aim is to fund the hub "with the objective of limiting reliance on new equity capital."
Pulsar listed four possible sources of funding, all at the discussion stage:
Financing channels under discussion
- University Bank, whose parent University Bancorp is a Pulsar shareholder, on part of the project
- Minnesota's Department of Employment and Economic Development
- USDA Rural Development, through its guaranteed business and industry loans
- Iron Range Resources & Rehabilitation, since the preferred site lies in its Taconite Assistance Area
Pulsar said no binding commitment has been received from the bank or any agency, and every option is subject to due diligence, credit approval and final terms. It had unaudited cash of about US$24.6 million at the date of the announcement.
Risks for shareholders
Pulsar is not yet producing helium and reported a net loss of US$19.4 million for the nine months to 30 June 2026. Its own risk statements say equity could still prove necessary if costs, lender demands or market conditions require it, which would dilute existing holders.
Several pieces are still missing. The company has to finalise a site in Lake County, choose an engineering, procurement and construction contractor, produce a full installed-cost estimate, and secure gas supply and buyers for the helium and CO2. Permits and an environmental review are also outstanding. Pulsar said early modelling suggests the hub could run as a stand-alone midstream business processing gas from third parties, but it has no processing customers yet. It also warned that helium and CO2 prices may change before any plant is commissioned.
Pulsar has not set a date for first commercial production. It said it will give one once the scope, permits, financing timetable and contractor schedule are better defined. The next fixed dates are TSXV approval of the Chart proposal and the 31 January 2027 payment.
Sources
- Pulsar Helium: Outlines development and project-financing strategy for commercial-scale helium and CO2 plant (12 October 2026)
- Pulsar Helium: Signs and accepts Chart Industries firm proposal for commercial-scale helium liquefaction plant (1 October 2026)
- Pulsar Helium: Financial and operating results for the third quarter ended 30 June 2026 (27 August 2026)