Skip to content
Markets

Serabi Gold Cuts Its 2026 Output Guidance as Coringa Permits Stall

Serabi Gold now expects 2026 output near 2025's 44,169 ounces, not over 53,000, as Coringa permits stall. Third-quarter production fell 9% to 11,008 ounces; cash stood at $63.2m with no debt.

The entrance portal of the Mina Serra underground mine at Serabi Gold's Coringa project, cut into a red-earth hillside below rainforest.
Photo: Serabi Gold

Serabi Gold, the Brazil-focused gold miner quoted in London, Toronto and on the OTCQX, has dropped its target of more than 53,000 ounces for 2026. It now expects output roughly in line with 2025's 44,169 ounces, because the permits it needs to move more ore from its Coringa mine have not arrived.

Third-quarter output slips 9%

Serabi produced 11,008 ounces of gold in the three months to 30 September, it said on 21 October. That is 9% less than the record 12,090 ounces of the same quarter in 2025 and almost exactly the 11,007 ounces of the second quarter. Output for the first nine months of 2026 reached 34,057 ounces.

The weak spot was the Palito Complex, the company's older mine and the site of its processing plant. Palito's mined grade fell to 4.01 grams per tonne, against 6.29 g/t a year earlier, and the company said grades were below budget. Palito produced 2,907 ounces in the quarter, down from 5,246 ounces a year before.

Coringa, the newer mine whose ore is trucked to the Palito plant, did the opposite. It produced 8,101 ounces, up from 6,843 ounces, from ore milled at 7.81 g/t. Over nine months Coringa supplied about 23,000 of the group's 34,057 ounces.

Serabi Gold: share price, chart and news

An underground loader driven by a miner in orange high-visibility clothing inside a rock tunnel at Serabi Gold's Coringa mine.
An underground loader driven by a miner in orange high-visibility clothing inside a rock tunnel at Serabi Gold's Coringa mine. Photo: Serabi Gold

Why the guidance was cut

Coringa runs under a GUIA, a three-year trial mining licence that allows Serabi to truck up to 100,000 tonnes of ore a year to the Palito plant. By 30 September, 85,602 tonnes had been moved against the current annual allowance. The licence expires on 29 January 2027, and until the limit is raised or a full operating licence is granted, extra stockpiled or newly mined Coringa ore cannot be sent to Palito.

The 53,000-ounce target had assumed one of two things: the GUIA allowance rising to 200,000 tonnes, or the full mining concession arriving in the fourth quarter. Neither has happened, so the planned fourth-quarter increase will not take place. Chief executive Mike Hodgson said the company could not deliver the increase because "these approvals have still not been received".

Serabi is working on two routes at once. With the national mining agency, the ANM, it is discussing the continuation of operations under the GUIA, backed by a legal petition. For the operating licence (LO), it needs FUNAI, the federal agency for Indigenous peoples, to approve an Indigenous component study that both Indigenous groups have already approved, and INCRA, the land agency, to sign off a change of land use at state and federal level.

One step was removed in September. After a site visit, Pará state's environmental agency, SEMAS, agreed that Serabi can skip the installation licence and apply directly for the LO, because Coringa will have no plant or tailings facility of its own. Once the LO is granted, the ANM can issue the mining concession that completes the permitting.

Gold over the last three months. Exchange data, delayed up to 15 minutes.
Gold over the last three months. Exchange data, delayed up to 15 minutes.

Cash, capacity and costs

Q3 2026

  • 11,008 oz gold produced, down 9% on a year earlier
  • $63.2m cash at 30 September, with no debt
  • 85,602 t of Coringa's 100,000-tonne annual allowance used

Cash fell from $65.7 million at the end of June, mainly because Serabi paid its first dividend, worth $5.1 million, in July. A further $3.4 million arrived on 1 October from bullion sold in September.

The fourth ball mill at Palito has been installed on time and on budget and is in final commissioning. The company says it lifts plant capacity from 650 to more than 900 tonnes a day and annual throughput to 330,000 tonnes in 2027, but that extra capacity needs Coringa ore to fill it.

At Coringa, the switch from manual selective mining to mechanised sublevel open stoping remains on track for the fourth quarter, with mining now under way in four zones. Spending on the Serra South and Galena zones was heavy in 2026, and Serabi expects materially lower capital spending in 2027. It is also assessing whether to restart São Chico, a small mine on care and maintenance since 2023, which would need a renewed GUIA.

Costs were already rising before the cut. In the first half of 2026, all-in sustaining costs were $2,682 an ounce against $1,792 a year earlier, while the average gold price received was $4,687.

What to watch

Next steps for Serabi

  • Late November 2026: third-quarter financial results and a further update to production guidance.
  • Before 29 January 2027: a decision by the ANM on extending the Coringa GUIA or raising its tonnage limit.
  • FUNAI and INCRA: the two approvals that would allow Serabi to apply for the Coringa operating licence.
  • Q1 2027: updated resource estimates for Palito and Coringa.

The risks are concentrated. Serabi's growth depends on Brazilian permits whose timing it does not control, and its 2026 output now rests on lower Palito grades improving in the fourth quarter, as the company expects, from the G3 vein. The balance sheet is debt-free, which gives it time, but production will not rise until the permits arrive.

Sources

Related stories

Investing

Serabi Gold: Investor Profile of the Brazilian Gold Miner Behind Palito and Coringa

Serabi Gold mines gold at Palito and Coringa in Brazil's Tapajós region. Its assets, first-half 2026 profit, cash and share count, the permit risks behind its guidance cut and the…

Markets

Ero Copper Reports Record Q3 Results and Cuts Net Debt to $353.5 Million

Ero Copper's Q3 2026 revenue rose to $348.0 million and adjusted EBITDA to $200.6 million, while net debt fell by about $99 million. Copper guidance held, but cost guidance rose.

Markets

Alkane Resources Starts FY27 With 40,740 Ounces and A$440m in Cash and Bullion

Alkane Resources produced 40,740 gold-equivalent ounces in the September quarter at an AISC of A$2,805, paid its first dividend and held A$440m in cash and bullion. Full-year…

Markets

Hycroft Mining Reports Its Best Hole Yet: 19.6m of 30.49 g/t Gold and 1,727 g/t Silver

Hycroft Mining's hole H26D-6175A cut 19.6 metres of 30.49 g/t gold and 1,726.72 g/t silver at Vortex, Nevada, its best result yet. What it shows, what it does not, and what comes…

Markets

Bitcoin Falls to $62,000 as $2bn of Leveraged Bets Are Wiped Out in Sixth Weekly Loss

Bitcoin fell to about $62,000 at the weekend as $2bn of leveraged bets were liquidated, its sixth straight weekly loss. It was back near $65,000 on Monday, with $60,000 the next…

Markets

Copper Hits a Four-Month Low at $13,210 as AI Doubts Drag European Miners Down 2.3%

Copper fell to $13,210 a tonne on Monday, a four-month low about 10% below September's record, as AI doubts and weak Chinese data hit metals and Europe's basic resources shares…

Markets

Bessent Urges an Outside CEO for Nvidia as Shares Fall 4.1% Before Results

Treasury Secretary Scott Bessent wants Nvidia to hire an outside chief executive, the board is not discussing Jensen Huang's return, and the shares fell 4.1% on Monday, a day…

Markets

Chip Index Sinks 5.28% With All 30 Stocks Down, Dragging the Nasdaq 2.49% Before Nvidia

The Philadelphia Semiconductor Index fell 5.28% on Monday 16 November with all 30 members down, pulling the Nasdaq 2.49% lower and the Dow down 739 points before Nvidia reports.