Anson Resources wants to build a 10,000-tonne-a-year lithium plant at Green River, Utah. The project now has its main permits, a POSCO demonstration plant on the way and US$406.5m of state incentives. What it lacks is money: the company held A$3.5m at the end of September against an estimated build cost of about US$569m.
What Anson Resources does
Anson Resources is listed on the Australian Securities Exchange under the code ASN, and its shares also trade in the US as ANSNF. It is a pre-revenue explorer and developer with no production.
Its core assets are lithium brine projects in the Paradox Basin in Utah, held through wholly owned US subsidiaries, A1 Lithium and Blackstone Minerals NV LLC. The flagship is the Green River Lithium Project, in the Leadville Limestone in Emery and Grand counties.
Anson also holds the Paradox Lithium Project, the Yellow Cat uranium-vanadium project in Utah, and several early-stage projects in Western Australia, where no field work was carried out in the September quarter. Bruce Richardson is executive chairman and chief executive.
Anson Resources: share price, chart and news

Green River and this year's milestones
Anson plans to pump lithium-bearing brine from deep wells, extract the lithium with direct lithium extraction (DLE) technology, and finish battery-grade lithium carbonate on site. The target is 10,000 tonnes a year of lithium carbonate equivalent (LCE), with first supply in 2029 under its scoping study.
| Green River key figures | Figure |
|---|---|
| Planned output | 10,000 t a year LCE |
| Upfront capital (scoping study) | About US$569m |
| C1 operating cost | US$3,837 a tonne |
| Post-tax NPV at 8% (scoping study) | US$896m |
| Post-tax NPV including Utah incentives | About US$1.05bn |
| Mineral resource | 773,000 t LCE |
| Ore reserve | None declared |
The scoping study, by engineering firm Burns & McDonnell, was released in May. On 7 October Anson said the Utah incentives lift the post-tax value by about US$150m to roughly US$1.05bn. A scoping study is a preliminary assessment, and Anson has warned it is not enough to support an ore reserve.
The resource was upgraded in May 2026 to 773,000 tonnes of LCE, of which 183,000 tonnes are indicated and 590,000 tonnes inferred, the lowest-confidence category. In the September quarter Anson added about 20.8 square kilometres of ground, including 1,175 acres of state mineral rights under the Green River and 17 state land blocks, whose lease has yet to be signed. It expects to fold the new ground into a resource update in the fourth quarter of 2026.
Milestones since July
- July: Small Mining Operation approval, which Anson calls the last major government permit for the plant
- July: first US$2.7m instalment of a US$5.2m facilitation fee from POSCO Holdings
- August: contractor JordProxa produced 99.6% pure lithium carbonate from Green River brine, confirmed by SGS
- September: Utah incentives of about US$406.5m approved, paid only after the plant operates
- September: non-binding offtake and financing memorandum with Wogen Resources America and Xcelsior Capital Advisors
- November: its iron removal process cut iron in a third-party brine from 13 ppm to zero
POSCO plans to design, build and run its own DLE demonstration plant at Green River at its own cost, using brine from Anson's Bosydaba #1 well. POSCO expects to start operating it in 2027 and finish test work in 2028.
The memorandum with Wogen and Xcelsior covers a possible offtake of about 2,000 to 6,000 tonnes a year of LCE from around 2029 or 2030 and possible financing. Anson stresses that it is non-binding and commits neither side to supply or funding.
On 10 November Anson said a test on another company's brine at its Lithium Innovation Center removed iron to below detectable levels in a single pass, with lithium content little changed. It has filed a patent application and is discussing a possible sale of the technology.
Cash, shares and spending
The balance sheet
- A$3.46m cash at 30 September 2026
- 1.62bn shares on issue, per ASX data
- A$1.59m spent on exploration and evaluation in the quarter
Anson had A$3,461,181 of cash at 30 September, up slightly from A$3,308,548 at 30 June. The quarter showed a net operating cash inflow of A$170,251, but only because of the first POSCO payment. Administration and corporate costs were A$1.36m.
The company said the definitive feasibility study, pre-development work and corporate costs will need more funding, which it aims to arrange with as little dilution as possible. The remaining POSCO instalments total about US$2.5m.
Anson has about 1.62 billion shares on issue, according to ASX market data.
Main risks
Funding is the biggest. The scoping study put the capital need at about US$568m to US$569m. Anson has said there is no certainty it can raise that much, and that money may come on terms that dilute existing holders. With A$3.5m in the bank, the company will need new capital well before construction.
The Utah incentives are paid only after the project is built and running, and depend on future taxes and property values. They do not provide cash now.
The project economics are preliminary. There is no ore reserve, most of the resource is inferred, and the DFS could change the cost and output estimates. The POSCO demonstration plant is meant to validate DLE on Green River brine, and its results will not be complete until 2028.
Lithium prices drive the returns. The scoping study's base case assumes lithium carbonate at US$16,465 a tonne in 2029, rising to US$30,123 by 2040. The offtake memorandum is non-binding.
What to watch next
| Event | Expected timing |
|---|---|
| Investor update webinar | 19 November 2026 |
| Green River resource update including the new ground | Fourth quarter of 2026 |
| Downstream flowsheet engineering by JordProxa | End of 2026 |
| Larger iron removal unit for the demonstration plant | End of 2026 |
| Definitive feasibility study | First quarter of 2027 |
| Yellow Cat phase 2 first assays | Early 2027 |
| POSCO demonstration plant start-up | 2027 |
The DFS is the main event. Anson says it will form the basis of funding talks with investors, partners and lenders in 2027.
Sources
- Anson Resources: September 2026 Quarterly Activities Report (ASX, 29 October 2026)
- Anson Resources: IMARC 2026 Presentation (ASX, 28 October 2026)
- Anson Resources: Iron Removal Pre-treatment Process Test Proves Successful on Third Party Brine (ASX, 10 November 2026)
- Anson Resources: Anson Engineering Study Confirms Green River as a Future Low-Cost Producer (ASX, 19 May 2026)
- Anson Resources: Anson Resources to Hold November Investor Update Webinar (ASX, 10 November 2026)
- ASX: Anson Resources key statistics