Skip to content
Business

Bannerman Energy Approves the Etango Uranium Mine Build, Targeting First Output in 2028

Bannerman Energy and CNNC's overseas arm have taken a final investment decision on Etango in Namibia: about US$353m of capital, 3.5m lb of uranium a year and first output targeted in 2028.

A Kobelco excavator digs at the Etango construction site in Namibia while two workers in hard hats and high-visibility clothing watch.
Photo: Bannerman Energy

Bannerman Energy and its joint venture partner from China's CNNC group have approved construction of the Etango uranium mine in Namibia. About US$353m of pre-production spending is to be paid from cash the venture already holds, and first yellowcake is targeted for 2028.

A go decision on Etango-8

The Etango joint venture took a positive final investment decision on the project on 23 October, Bannerman Energy told the Australian Securities Exchange. Bannerman owns 55% of the venture and CNNC Overseas Limited (CNOL) owns 45%. The venture in turn holds 95% of the Etango Uranium Project.

The decision covers the base Etango-8 design set out in the definitive feasibility study of December 2022. Bannerman said the material assumptions behind that study still apply and have not materially changed. The plan forecasts average output of about 3.5 million pounds of uranium oxide (U3O8) a year, with commissioning and first production targeted during 2028. Full-scale construction is due to begin over the coming months.

Etango at the investment decision

  • US$353m forecast pre-production capital (±10%)
  • 3.5m lb average annual U3O8 output
  • 2028 targeted first production

Bannerman Energy: share price, chart and news

Aerial view of the Etango site after blasting of the stockpile tunnel and the terraces for the secondary and tertiary crushers.
Aerial view of the Etango site after blasting of the stockpile tunnel and the terraces for the secondary and tertiary crushers. Photo: Bannerman Energy

About US$64m of the capital budget had already been spent on early works by 30 September, including cash held in the Namibian operating subsidiary. That leaves roughly US$289m by simple subtraction, which is to be met from the joint venture's existing cash of about US$295m at the same date, excluding the subsidiary's cash.

Bannerman held about A$175m of its own cash at 30 September, outside the joint venture. It says that money fully funds its share of working capital through construction, ramp-up and into commercial production. The venture will only call on Bannerman for that share once most of its existing cash has been spent.

No debt is part of the plan. "Today's FID by the Etango JV is a defining moment for Bannerman," said managing director and chief executive Gavin Chamberlain, who described the build as funded on a debt-free basis. He also pointed to a cornerstone offtake framework on market-based terms. The announcement did not set out volumes or prices.

Uranium (Sprott trust) over the last three months. Exchange data, delayed up to 15 minutes.
Uranium (Sprott trust) over the last three months. Exchange data, delayed up to 15 minutes.

Where the site stands

Etango received its mining licence in December 2023 and holds all its environmental approvals, according to the company. Early works began in January 2024. Bannerman says bulk earthworks are substantively complete, detailed design is well advanced and key supporting infrastructure is either finished or well under way.

Alongside the decision, Danie van Aswegen was named chief executive of the Namibian operating company, Bannerman Mining Resources Namibia. He has served as chief operating officer for Namibia since October 2025.

A larger version of the mine remains an option. A scoping study published in March 2024 pointed to capacity to expand output to 6.7 million pounds a year, but that case is not part of the approved plan.

Key points

  • The Etango JV (Bannerman 55%, CNOL 45%) approved construction on 23 October 2026.
  • Forecast pre-production capital is about US$353m, of which about US$64m has been spent.
  • JV cash of about US$295m covers the rest; Bannerman holds about A$175m for its working capital share.
  • First production is targeted for 2028, at about 3.5m lb U3O8 a year.

The risks that remain

A final investment decision turns Etango from a development project into a construction project, but the main risks for a single-asset company stay in place. The capital estimate carries a range of plus or minus 10%, and any overrun beyond the joint venture's cash would need new money from the partners. Bannerman's own cash is earmarked for working capital, not for cost overruns.

Revenue will depend on uranium prices when the mine starts selling, and a build in Namibia carries the usual exposure to delays in power, water and supplies. Key decisions are shared with a state-owned partner. Until first production, Bannerman will have no mining income and will rely on the cash it holds today.

Sources

Related stories

Investing

Bannerman Energy Profile: Building Namibia's Etango Uranium Mine With a CNNC Partner

Bannerman Energy is building the Etango uranium mine in Namibia with CNNC's overseas arm. Its cash, share count, mine plan, sales terms and the dates to watch before first output…

Business

Reconnaissance Energy Africa Starts Horizontal Drilling at KW1X, Flow Test Due by Year-End

ReconAfrica has started a sidetrack of up to 1,000 metres at its Kavango West 1X discovery in Namibia, funded by a C$21.9m share sale, and expects to publish flow test results…

Business

Paladin Energy Raises A$525 Million to Push Its Canadian PLS Uranium Project Towards 2031

The uranium miner sold about 67 million new shares at A$7.80, a 10.3% discount, to fund early works at Patterson Lake South in Saskatchewan, more drilling and the repayment of its…

Business

Munich Re Raises Its 2026 Profit Goal to €6.6bn as Disaster Losses Come In Low

Munich Re earned about €1.7bn in the third quarter, beating the €1.479bn consensus, and raised its 2026 profit target to €6.6bn from €6.3bn as major losses came in below budget.

Business

Québecor Makes a C$31bn Cash-and-Share Bid for Telus, Which Warns of Regulatory Risk

Québecor has offered C$6.35 in cash plus 0.17 of its own shares for each Telus share, a bid worth about C$31bn. The Telus board says the price falls short and the regulatory risk…

Business

Tyson Foods Shares Jump 8.7% as Beef Outlook Outweighs a $74m Quarterly Loss

Tyson Foods posted a $74m fourth-quarter net loss and adjusted EPS of $0.61, down 47%, yet its shares closed 8.7% higher on Monday as its 2027 beef outlook pointed to far smaller…

Business

Roche Wins FDA Approval for Breast Cancer Pill Wilserdly After 62% Cut in Progression Risk

The FDA approved Roche's all-pill Wilserdly combination for ESR1-mutated advanced breast cancer after it cut the risk of progression or death by 62%. A ruling on early-stage use is…

Business

ULA Loses Its First Mission as Vulcan Rocket Fails With 40 Amazon Leo Satellites on Board

United Launch Alliance's Vulcan rocket failed about 10 minutes after lift-off on Sunday, and all 40 Amazon Leo satellites were lost. Amazon fell 3.3% on Monday as space stocks…