DMG Blockchain Solutions has pushed back the date for its first AI customers at Christina Lake, British Columbia. In an update issued on 14 September 2026, the bitcoin miner said it is now realistically looking to 2027 to power up tenant servers, rather than the end of 2026 it had aimed for. A 50 megawatt colocation deal with an unnamed tenant is still only a letter of intent.
A later start, and why
DMG is converting its Christina Lake facility, today used for bitcoin mining, into a data centre that would house other companies' AI servers. That business is known as colocation: DMG would supply the building, power, cooling and connectivity, and the tenant would bring the computers.
The company had set the end of 2026 as its goal for tenant servers to be running. It says that target was always on a commercially reasonable efforts basis and partly depended on signing a definitive agreement quickly. No such agreement has been signed. DMG said it will issue a full release if and when one is.
The letter of intent, first announced in June, covers 50 megawatts of critical IT load, the power used by the servers themselves.
DMG Blockchain Solutions: share price, chart and news
Power, building and fibre
Christina Lake in numbers
- 75 MW of contracted power, 60 MW non-firm and 15 MW firm
- 50 MW of critical IT load under the letter of intent
- 150 MW of firm power applied for, still in process
The site now has 75 MW of power, after DMG contracted an extra 10 MW of non-firm supply. Its own substation can already carry the full load. DMG says that, even at a worst-case power usage effectiveness of 1.5, 75 MW could support more than 50 MW of IT load, and that the climate, newer servers and other cooling options could add headroom.
A separate application for up to 150 MW of firm power is still being processed. DMG expects to push it forward once a definitive agreement is signed, possibly alongside the existing non-firm supply, depending on the utility's transmission capacity.
On the building, DMG has applied for a permit for an extension that would roughly double its space and support up to 60 MW of IT load. It is in the late stages of picking a general contractor with data centre experience, has chosen an architect and is selecting a mechanical engineering firm for cooling. It is also weighing prefabricated units against building on site.
Two telecom providers have been contracted for two separate 100 gigabit-per-second fibre routes, which can be upgraded to 400 gigabits later. DMG said it committed material capital to connectivity before any tenant contract was signed, without giving a figure.
Funding still to be arranged
DMG has not disclosed a budget for the conversion. It says it is talking to several financial institutions about rated bonds, credit lines and equity or convertible debt, aiming for a low cost of capital and as little dilution as possible. No terms have been agreed.
At 30 June, the end of its fiscal third quarter, DMG held C$41.6 million in cash, short-term investments and digital assets, of which C$31.6 million was digital currency and C$2.8 million was cash. It also had C$19.7 million of loans payable within a year. Revenue in that quarter fell 45% from a year earlier to C$6.4 million as hashrate dropped to 1.47 exahashes per second, and the net loss was C$3.9 million.
Chief executive Sheldon Bennett said he believes DMG can become "a leader in Canada for offering AI data center colocation services".
Risks to weigh
- The 50 MW tenant deal is still only a letter of intent; a definitive agreement may not follow
- Financing for the build is not in place and could dilute shareholders if it includes equity
- Some local residents oppose the project; DMG says it will not raise utility rates and will use less water and make less noise than bitcoin mining
- Revenue fell 45% year on year in the latest quarter, and the company is loss-making
What to watch
The next milestones are a definitive agreement with the tenant, a financing package, the building permit and the choice of general contractor. DMG's fiscal year ends on 30 September, so annual results are the next scheduled report.
Sources
- DMG Blockchain Solutions Provides Update on its Christina Lake AI Data Center Conversion (DMG Blockchain Solutions, 14 September 2026)
- News releases (DMG Blockchain Solutions)
- DMG Blockchain Solutions Reports Third Quarter 2026 Financial Results (InvestorNews, release of 27 August 2026)