Skip to content
Investing

Graphite One Profile: Alaska's Graphite Creek Deposit and an Ohio Anode Plant Plan

Graphite One wants to build a US graphite supply chain from an Alaskan deposit to an Ohio anode plant. It has no revenue, US$20.1 million in cash and a going-concern warning. Here is what to watch.

Aerial view of Graphite One's camp of white tents and buildings on the tundra below the hills at Graphite Creek, Alaska.
Photo: Graphite One

Graphite One is a Vancouver-based development company that wants to build a United States supply chain for battery anode material, from a graphite deposit in Alaska to a plant in Ohio. It has no revenue yet, US$20.1 million in cash at the end of September and a going-concern warning in its own filings. This profile sets out what it owns, its latest numbers and the dates that matter.

What the company does

Graphite One's plan has two linked parts. In Alaska it is permitting the Graphite Creek deposit on the Seward Peninsula, about 55 km north of Nome. The US Geological Survey describes it as the largest known graphite deposit in the country. In Ohio it plans a plant in Conneaut that would turn graphite into active anode material, the powder that forms the negative electrode of lithium-ion batteries in electric vehicles and energy storage systems.

The company reports in US dollars and trades on the TSX Venture Exchange under GPH and over the counter in the US as GPHOF. It has generated no operating revenue to date.

Graphite One: share price, chart and news

Close-up of dark grey graphite drill core from Graphite Creek lying in a core box beside a pen for scale.
Close-up of dark grey graphite drill core from Graphite Creek lying in a core box beside a pen for scale. Photo: Graphite One

The latest numbers

The third-quarter filings, approved on 12 November, show a company spending more as it moves toward construction.

ItemQ3 2026 filings
Net loss, Q3$3.2 million (Q3 2025: $2.3 million)
Net loss, nine months$9.7 million (2025: $5.8 million)
Cash at 30 September$20.1 million (31 Dec 2025: $8.4 million)
Working capital$17.7 million
Cash used in operations, nine months$10.7 million
Accumulated deficit$73.5 million

Cash rose because of a February 2026 public offering that raised C$35.0 million gross, about $23.7 million net, plus C$8.6 million from warrant exercises. The company says the rest of the offering money should be used by the second quarter of 2027.

The higher loss came mainly from online marketing to European and US investors, which cost $2.3 million more in the nine months than a year earlier, and from development costs for the Ohio plant. In October the company signed an agreement with Frontier Media for marketing services at $250,000 a month for six months.

Share structure at 12 November 2026

  • 209.7m common shares outstanding
  • 276.8m shares fully diluted
  • 41.8m warrants, average exercise price C$1.62

The fully diluted count adds options, restricted and performance share units and warrants. At C$0.67, the 12 November close, the warrants sit well above the share price.

Graphite Creek, Alaska

A feasibility study filed in April 2025 models a 20-year mine feeding a secondary treatment plant that would make 256,000 tonnes a year of graphite products at full capacity. The company's project page gives an after-tax net present value of $5 billion at an 8% discount rate and a 27% internal rate of return. Those figures come from a study with long-dated price and cost assumptions and are not a forecast of returns.

Federal permitting moved from an environmental assessment to a full environmental impact statement in September 2026. The FAST-41 federal dashboard now shows the US Army Corps of Engineers completing that process in September 2027. The company's 2 November release targets mine construction in 2028 and production in 2030; its July statement on the switch to an impact statement referred to a 2029 start, so the timetable is worth checking in each update.

On 10 November Graphite One started a three-month program with Ames National Laboratory to test whether rare earths, including dysprosium, yttrium and scandium, can be recovered from garnet in the deposit. The company says there is no certainty they can be extracted economically. In October it also won a Defense Logistics Agency award, of undisclosed value, to test carbon materials from the deposit for high-temperature defence uses.

Ohio Phase 1

The first step is a 10,000-tonne-a-year finishing and blending plant in Conneaut that would use purchased material, so it could sell product before the mine exists. The estimated initial cost is US$80 million, to be updated after engineering. The Ohio EPA issued the final air permit on 27 October; other state and local permits are still needed.

Chief executive Anthony Huston said: "Ohio lets us pursue customer sales, generating company revenue, before mine production begins."

The company holds non-binding letters of interest from the Export-Import Bank of the United States totalling US$2.07 billion and non-binding supply agreements with Lucid Motors. None of these is a firm commitment.

Main risks

What could go wrong

  • Going concern: the filings say more financing is needed within twelve months and that there is material uncertainty
  • Dilution: equity raises and 67 million potential shares from options, units and warrants
  • Financing: the US$80 million plant and the far larger mine have no committed funding
  • Permits: the Alaska mine is in a full federal impact statement process with state permits to follow
  • Customers: product qualification and binding offtake are not yet in place
  • Policy: the case relies on US supply-chain policy and China's export controls, both of which can change

The shares have fallen from C$1.01 on 3 September to C$0.67 on 12 November.

What to watch

DateEvent
Early 2027End of the three-month Ames rare earth program begun on 10 November
By April 2027Target for Ohio final investment decision, construction contract and start of works
By Q2 2027Company expects to have used the February 2026 offering proceeds
September 2027Scheduled federal impact statement and Army Corps decision on Graphite Creek
Q4 2028Target for first sales from Ohio Phase 1

Sources

Related stories

Business

Graphite One Wins Final Ohio Air Permit for Planned US$80 Million Anode Plant

Ohio's environmental regulator has issued Graphite One the air permit for its planned 10,000-tonne anode material plant in Conneaut. Engineering, other permits and financing are…

Investing

Sovereign Metals Profile: Kasiya's Rutile, Graphite and Rare Earths in Malawi

Sovereign Metals wants to build Kasiya in Malawi, a large natural rutile and graphite mine with a rare earth by-product. What its studies say, its cash, permits, risks and what to…

Investing

Talga Group: An Investor Profile of the Swedish Graphite Anode Developer

Talga Group mines no graphite yet, but it sells small volumes of anode from a Swedish demonstration plant. Its assets, customers, cash, share count, risks and the dates that matter…

Investing

Sunrise Energy Metals: Building a Scandium Mine With US Backing and a Nasdaq Plan

Sunrise Energy Metals is building the Syerston scandium mine in New South Wales. We look at the project numbers, cash, the US$400m US loan offer, the Nasdaq plan, risks and dates…

Investing

Aya Gold & Silver Corrects Q3 Cash Costs to $14.28 an Ounce After Silver Double Count

Aya Gold & Silver refiled its Q3 MD&A after silver in transit was deducted twice. Zgounder ounces sold rise to 1,392,478 and cash costs fall to $14.28 from $15.51. Revenue and…

Investing

FDA Rejects Summit's Lung Cancer Drug Ivonescimab Over Phase 3 Survival Miss

The FDA has rejected Summit Therapeutics' lung cancer drug ivonescimab, saying slower tumour growth in the phase 3 HARMONi trial was not enough without a clear gain in survival.

Investing

Red Cat Withdraws Its $150m to $180m 2026 Revenue Target After $11.8m Third Quarter

Red Cat Holdings has withdrawn its $150m to $180m revenue target for 2026 after third-quarter sales of $11.8m, blaming slower defence funding. Its quarterly net loss more than…

Investing

Berkshire Reveals $689m Bending Spoons Stake, Doubles Lennar and Trims Bank of America Again

Berkshire Hathaway's third-quarter 13F shows a new Bending Spoons stake worth $689m, a doubled Lennar holding and 27.5 million more Bank of America shares sold, while Apple stayed…