Vizsla Silver ended its first fiscal quarter with US$406.5 million of cash, enough for the company to call itself well funded, but site work at its Panuco silver-gold project in Mexico remains suspended. Exploration and underground development have been paused since the end of January, after ten people were taken from the company's project site in Concordia, Sinaloa. Nine of them were later found dead and one remains missing.
The quarter in numbers
Vizsla, listed in Toronto and New York, filed its results for the three months to 31 July 2026 on 4 September. Its fiscal year ends on 30 April, so this is the first quarter of fiscal 2027. The company reports in US dollars.
It made a net loss of US$19.8 million, or US$0.06 a share, against a net profit of US$1.2 million a year earlier. Several items drove the swing:
- General and administrative costs rose to US$12.1 million from US$7.4 million, mainly because of higher share-based pay (up US$2.1 million), the cost of holding the project while it is paused (up US$1.8 million) and professional fees (up US$0.6 million).
- A stronger US dollar produced a foreign exchange loss of US$3.3 million, compared with a US$2.3 million gain a year before.
- A deferred Mexican special mining duty charge of US$5.5 million appeared for the first time.
- Interest and finance income rose to US$4.3 million from US$1.7 million, helped by the cash raised from convertible notes.
First quarter of fiscal 2027
- US$406.5m cash at 31 July, down from US$427.3m in April
- US$19.8m net loss for the quarter
- 355.1m shares outstanding on 4 September
Vizsla Silver: share price, chart and news
Where Panuco stands
Panuco is the project the company plans to build. Its feasibility study, completed in November 2025 by Ausenco, estimated an after-tax net present value of US$1.8 billion at a 5% discount rate and an internal rate of return of 111%, at prices of US$35.50 an ounce for silver and US$3,100 for gold. Initial capital is put at US$238.7 million. Reserves stand at 12.8 million tonnes grading 416 g/t silver-equivalent, supporting average output of 17.4 million silver-equivalent ounces a year over an initial 9.4-year mine life.
During the quarter the team kept working remotely. Detailed engineering continued, underground mining contractors were identified and procurement of plant equipment began. In June Vizsla awarded FLSmidth an equipment supply agreement for the main process plant; early engineering is under way under a limited notice to proceed while final terms are agreed.
On site, nothing moved. No underground development took place in the quarter, leaving 852 metres completed against a planned scope of about 1,070 metres. There was no exploration drilling either. The quarterly report gives no date for a return to site; in its 27 August circular to shareholders, the company said it expects to return by the end of 2026, subject to security conditions. The company has not made a production decision; it says construction depends on completing permitting. In August it repeated its target of first silver in the second half of 2027.

Financing and balance sheet
Most of the cash came from US$300 million of convertible notes sold in November 2025. They pay 5% a year, mature on 15 January 2031 and convert at US$5.84 a share, which would mean about 51.4 million new shares if all were converted. Vizsla also bought a capped call, which offsets dilution up to a share price of US$10.51.
The company has a working capital facility of 173 million Mexican pesos, about US$10 million, with FIFOMI, a Mexican government financial institution. It was undrawn at the end of August. In the year-earlier quarter, Vizsla sold 3.1 million shares through an at-the-market programme for gross proceeds of about US$9.7 million.
At quarter end, a deal for Elemental Royalty to buy Vizsla Royalties, which holds royalties on Panuco, was still awaiting closing. Vizsla Silver's own interest in Vizsla Royalties, carried at about US$7.0 million, would be removed from its books on completion. Vizsla Silver closed at C$5.74 in Toronto on 3 September, up from C$4.38 at the end of July.
Risks for shareholders
What to keep in mind
- Security: the January incident showed the danger to staff in the region, and the planned return to site by the end of 2026 depends on security conditions.
- Timing: the second-half 2027 production target depends on a construction decision, permits and financing, none of which is complete.
- Volatile results: changes in the fair value of the note-linked derivative and capped call can swing reported profit and loss.
- Dilution: conversion of the notes and 18.2 million outstanding options would add to the share count.
- Holding costs rise while the site is idle, and a stronger US dollar has already hit results.
Sources
- Vizsla Silver: Condensed interim consolidated financial statements, three months ended 31 July 2026 (SEC filing, 4 September 2026)
- Vizsla Silver: Management's Discussion and Analysis, three months ended 31 July 2026 (SEC filing, 4 September 2026)
- Vizsla Silver: Notice of Meeting and Management Information Circular (27 August 2026)
- Vizsla Silver: Vizsla Silver Appoints Luis Lázaro as President, Mexico (5 August 2026)
- Vizsla Silver: Vizsla Silver Provides Additional Update on Situation in Concordia (6 April 2026)