Skip to content
Markets

Denison Mines Puts Phoenix Uranium Mine at 24% Complete and Trims Its 2026 Build Spend

Denison Mines' Phoenix uranium mine in Saskatchewan was about 24% built at the end of September and still targets output in the second half of 2028, but a slow start cut C$26.6m from 2026 spending.

Aerial view of the Phoenix ISR uranium mine site in northern Saskatchewan on 28 September 2026, with cleared sand pads, wellfield civil works, equipment and site buildings beside a forest and lake.
Photo: Denison Mines

Denison Mines said its Phoenix in-situ recovery uranium mine in northern Saskatchewan was about 24% complete at the end of September, after its first quarter of full-scale construction. The company still targets first production in the second half of 2028, but it cut its 2026 construction spending forecast by C$26.6 million after a slower than planned start on site.

A first quarter of full-scale building

Denison, listed in Toronto and on NYSE American, filed its third-quarter accounts on 4 November. Phoenix is part of the Wheeler River project, in which Denison holds an effective 95% interest. Federal approval of the environmental assessment and a construction licence came in February 2026, early site works began in March and full-scale construction started in July.

The company estimated total project completion at roughly 24% on 30 September. Engineering, procurement, construction management and owner's costs were 32% complete, equipment fabrication and delivery 32%, and construction itself 20%.

Spending is running ahead of the work visible on site because Denison buys key components directly and has much of the plant fabricated off site in modules. Phoenix spending in the first nine months of 2026 reached C$161.1 million, including C$105.0 million on construction and indirect costs and C$39.0 million on equipment and materials.

Denison Mines: share price, chart and news

Phoenix at 30 September 2026

  • 24% estimated total project completion
  • C$161.1m spent on Phoenix in the first nine months
  • H2 2028 targeted first production
Overhead view of the Phoenix process plant foundations under construction on 28 September 2026, with rebar grids and concrete raft slabs.
Overhead view of the Phoenix process plant foundations under construction on 28 September 2026, with rebar grids and concrete raft slabs. Photo: Denison Mines

Why the 2026 budget came down

Denison lowered its 2026 forecast for Phoenix construction spending by C$26.6 million. It blamed a later than expected start to site clearing, a slower ramp-up to full-scale work because of regional flooding and restrictions on site access, and weather delays once building was under way. The full-year Phoenix forecast now stands at C$278.6 million, with about C$117.5 million expected in the fourth quarter.

Freeze drilling, which builds the frozen ground barrier that the in-situ method relies on, fell behind over the summer. By the end of October casing was in place for all 66 freeze holes planned for the first wellfield area, but only 15 had been drilled to full depth. The rig count has risen from one to four, and Denison expects freeze drilling to finish by the end of the first quarter of 2027.

Other work is further along. Site civil work was about 47% complete at the end of October, the main access road from Highway 914 is in use, and the airstrip is targeted to open before the end of 2026, weather permitting. Energisation of the substation is forecast for the first quarter of 2027. Of 129 procurement and construction packages, 99 had been awarded by 30 September.

Uranium (Sprott trust) over the last three months. Exchange data, delayed up to 15 minutes.
Uranium (Sprott trust) over the last three months. Exchange data, delayed up to 15 minutes.

A profit on paper and a smaller cash pile

Denison reported third-quarter net income of C$81.8 million, or C$0.09 a share, against a net loss of C$135.0 million a year earlier. The swing came mostly from a non-cash gain of C$110.8 million as the value of the conversion features on its US$345 million convertible notes fell; that value moves with Denison's share price. Over nine months the company recorded a net loss of C$7.5 million. Revenue, which comes from toll milling of Cigar Lake ore at the McClean Lake mill, was C$1.0 million in the quarter.

Cash and equivalents fell to C$362.7 million at 30 September from C$465.9 million at the end of 2025. Denison also held 950,000 pounds of physical uranium valued at C$121.0 million, plus 182,004 pounds of concentrate inventory. It sold 750,000 pounds in the second quarter at an average of US$89.17 a pound, and has committed 600,000 pounds for delivery between the fourth quarter of 2026 and the second quarter of 2027. Prices are fixed on 350,000 of those pounds, for expected proceeds of US$33.3 million.

Contracts and exploration

Including near-term deliveries, Denison has firm sales commitments for more than 8 million pounds of uranium and is in advanced talks on more than 5 million pounds more. Most of that volume is due after 2028 from Phoenix output, and most is priced on a market-related basis.

At Phoenix North, drilling in October returned 0.67% eU3O8 over 2.5 metres in hole WR-868, and mineralisation now spans more than 100 metres of strike. Drilling continues into the fourth quarter.

The risks

Until Phoenix produces, Denison earns only small toll-milling revenue, so the build is funded from cash, uranium sales and the convertible notes. The company itself notes that its completion estimates can shift with contractor and labour availability and weather, and the slow start to freeze drilling shows how one critical task can move a schedule. Further cost increases or a weaker uranium price would put pressure on that funding mix, and with 905.4 million shares in issue, any new equity raise would dilute existing holders.

Sources

Related stories

Investing

Denison Mines Investor Profile: Wheeler River, the Phoenix Build and the Road to 2028

Denison Mines is building Phoenix, a high-grade in-situ uranium mine in Saskatchewan, with first output targeted for late 2028. Its assets, latest numbers, funding, risks and the…

Markets

NexGen Energy Starts Rook I Shaft Work, Holds C$822m in Cash and Investments

NexGen Energy awarded the shaft-sinking contract for its Rook I uranium mine and began shaft work in September. It held C$821.6m of cash and investments but needs more money to…

Markets

Peninsula Energy Says Lance Flow Rates Are Recovering and Holds Its 2027 Uranium Target

Peninsula Energy says wellfield changes at its Lance uranium project in Wyoming have lifted flow rates, but the September quarter produced only 17,968 pounds and 2026 has no…

Markets

Boss Energy Keeps Its FY27 Guidance as Honeymoon Output Holds Steady Through Heavy Rain

Boss Energy kept its FY27 guidance after Honeymoon produced 359,000 pounds of uranium in the September quarter despite heavy rain, with costs below the annual range, while its…

Markets

Bitcoin Falls to $62,000 as $2bn of Leveraged Bets Are Wiped Out in Sixth Weekly Loss

Bitcoin fell to about $62,000 at the weekend as $2bn of leveraged bets were liquidated, its sixth straight weekly loss. It was back near $65,000 on Monday, with $60,000 the next…

Markets

Copper Hits a Four-Month Low at $13,210 as AI Doubts Drag European Miners Down 2.3%

Copper fell to $13,210 a tonne on Monday, a four-month low about 10% below September's record, as AI doubts and weak Chinese data hit metals and Europe's basic resources shares…

Markets

Bessent Urges an Outside CEO for Nvidia as Shares Fall 4.1% Before Results

Treasury Secretary Scott Bessent wants Nvidia to hire an outside chief executive, the board is not discussing Jensen Huang's return, and the shares fell 4.1% on Monday, a day…

Markets

Chip Index Sinks 5.28% With All 30 Stocks Down, Dragging the Nasdaq 2.49% Before Nvidia

The Philadelphia Semiconductor Index fell 5.28% on Monday 16 November with all 30 members down, pulling the Nasdaq 2.49% lower and the Dow down 739 points before Nvidia reports.