Skip to content
Markets

NexGen Energy Starts Rook I Shaft Work, Holds C$822m in Cash and Investments

NexGen Energy awarded the shaft-sinking contract for its Rook I uranium mine and began shaft work in September. It held C$821.6m of cash and investments but needs more money to finish the build.

Aerial view of fresh earthworks at the Rook I site in northern Saskatchewan: a passenger plane stands on newly graded ground beside a lined water pond, with forest and lakes beyond.
Photo: NexGen Energy

NexGen Energy has awarded the contract to sink the shafts at its Rook I uranium project in Saskatchewan and began shaft preparation work on 28 September. Third-quarter accounts filed on 9 November show C$821.6 million of cash and short-term investments, but the company says it will still need further financing to complete construction.

Shaft work starts on the critical path

NexGen, listed in Toronto and New York under NXE and on the ASX under NXG, began licensed construction at Rook I on 8 June 2026. That followed the Canadian Nuclear Safety Commission's approval of the environmental assessment in March and its licence to prepare the site and construct. A groundbreaking ceremony for major construction was held on 13 August.

The main event of the third quarter came on 11 September, when NexGen awarded the shaft-sinking contract after a competitive tender and commercial negotiations. The company said the award allowed final detailed engineering to be completed, and shaft preparation construction began on 28 September. It describes the project as materially on schedule, on budget and to scope.

In the fourth quarter the company is preparing the ground around the production and exhaust shafts so that temporary freezing and pre-sinking can start in the first quarter of 2027. It is also awarding more contracts, including civil works, concrete and power generation, and extending the airstrip runway to 5,840 feet.

NexGen Energy: share price, chart and news

NexGen at 30 September 2026

  • C$821.6m cash and short-term investments
  • 2.7m lb of uranium held in strategic inventory, at a cost of C$341.2m
  • C$22.3m third-quarter net loss
An excavator loads articulated haul trucks at dusk during earthworks at the Rook I site.
An excavator loads articulated haul trucks at dusk during earthworks at the Rook I site. Photo: NexGen Energy

A smaller loss, mostly from accounting moves

The net loss narrowed to C$22.3 million, or C$0.03 a share, from C$129.2 million a year earlier. Most of the improvement came from a C$25.6 million non-cash gain on revaluing the company's convertible debentures, compared with a C$95.2 million loss on the same line a year before. Share-based payments rose to C$30.1 million from C$11.1 million as more options vested, and office, administration and travel costs almost doubled to C$10.5 million as the project team grew. The nine-month loss was C$103.8 million.

NexGen has no revenue other than interest on its cash. Cash fell by C$235.4 million in the first nine months of 2026, including C$159.5 million spent on Rook I engineering, procurement and construction and C$99.8 million on exploration and pre-licence development work.

DAX over the last three months. Exchange data, delayed up to 15 minutes.
DAX over the last three months. Exchange data, delayed up to 15 minutes.

Debentures turn into shares

The US$110 million of 2023 convertible debentures held by Queen's Road Capital and Washington H. Soul Pattinson have now been fully converted into shares. A holder converted US$40 million on 15 September for 5,917,159 shares plus 29,844 shares for interest. The remaining US$70 million converted on 22 October for 10,355,029 shares plus 86,899 shares for interest.

The conversions removed debt but added shares: NexGen had 688,034,761 shares outstanding on 9 November. US$250 million of 2024 debentures, issued to MMCap in exchange for the 2.7 million pounds of uranium, remain outstanding.

Paying for the peak years

The construction budget was last updated in an internal trend report in August 2024, which raised estimated pre-production capital to about C$2.2 billion from C$1.3 billion in the 2021 feasibility study. NexGen's filing states that it will continue to require additional financing to complete construction.

On the conference call on 10 November, chief executive Leigh Curyer said cash and short-term investments fund the company to the end of the third quarter of 2027. He said new funding was likely to combine strategic financing, prepayments and project finance, with timing not yet decided, and that the uranium inventory would not be sold to fund the build. Asked whether an analyst's estimate of about C$600 million of spending in 2027 was the right way to think about it, he said yes and confirmed 2027 as the expected peak year.

What to watch

Next milestones

  • The 42,000-metre drill programme at Patterson Corridor East, 28,712 metres complete at 30 September, is due to finish in early December.
  • Temporary freezing and pre-sinking at the shafts are planned for the first quarter of 2027.
  • Any financing deal, whether strategic investment, uranium prepayments or project debt, and its effect on existing shareholders.

The risks are those of a large mine build without revenue: cost inflation against a budget not formally revised since 2024, the size of the remaining funding need, possible dilution from new equity or the outstanding debentures, and the uranium price.

Sources

Related stories

Investing

NexGen Energy Investor Profile: Building Rook I, a Large High-Grade Uranium Mine

NexGen Energy is building Rook I around the Arrow uranium deposit in Saskatchewan. What it owns, the expected cost of the mine, its latest numbers, the funding gap, the risks and…

Markets

Denison Mines Puts Phoenix Uranium Mine at 24% Complete and Trims Its 2026 Build Spend

Denison Mines' Phoenix uranium mine in Saskatchewan was about 24% built at the end of September and still targets output in the second half of 2028, but a slow start cut C$26.6m…

Markets

Peninsula Energy Says Lance Flow Rates Are Recovering and Holds Its 2027 Uranium Target

Peninsula Energy says wellfield changes at its Lance uranium project in Wyoming have lifted flow rates, but the September quarter produced only 17,968 pounds and 2026 has no…

Markets

Boss Energy Keeps Its FY27 Guidance as Honeymoon Output Holds Steady Through Heavy Rain

Boss Energy kept its FY27 guidance after Honeymoon produced 359,000 pounds of uranium in the September quarter despite heavy rain, with costs below the annual range, while its…

Markets

Bitcoin Falls to $62,000 as $2bn of Leveraged Bets Are Wiped Out in Sixth Weekly Loss

Bitcoin fell to about $62,000 at the weekend as $2bn of leveraged bets were liquidated, its sixth straight weekly loss. It was back near $65,000 on Monday, with $60,000 the next…

Markets

Copper Hits a Four-Month Low at $13,210 as AI Doubts Drag European Miners Down 2.3%

Copper fell to $13,210 a tonne on Monday, a four-month low about 10% below September's record, as AI doubts and weak Chinese data hit metals and Europe's basic resources shares…

Markets

Bessent Urges an Outside CEO for Nvidia as Shares Fall 4.1% Before Results

Treasury Secretary Scott Bessent wants Nvidia to hire an outside chief executive, the board is not discussing Jensen Huang's return, and the shares fell 4.1% on Monday, a day…

Markets

Chip Index Sinks 5.28% With All 30 Stocks Down, Dragging the Nasdaq 2.49% Before Nvidia

The Philadelphia Semiconductor Index fell 5.28% on Monday 16 November with all 30 members down, pulling the Nasdaq 2.49% lower and the Dow down 739 points before Nvidia reports.