Ivanhoe Electric has published an updated preliminary feasibility study for its Santa Cruz copper project in Arizona. The study gives an after-tax net present value of $1.5bn at a copper price of $4.75 a pound, an upfront cost of $1.43bn and first copper cathode in 2029.
The headline economics
The 2026 study, released before the US market opened on 23 September, models an underground mine producing about 75,000 tonnes of copper cathode a year on average over its first 15 years, with a total life of 24 years. Ore would be processed by heap leaching and solvent extraction and electrowinning (SX-EW), producing 99.99% pure cathode on site with no need for a smelter.
At the base-case copper price of $4.75 a pound, the study shows an after-tax NPV of $1.5bn at an 8% discount rate, an internal rate of return of 19% and payback in 4.8 years from the start of operations. At the spot price of $6.79 a pound on 21 September, the NPV rises to $3.5bn, the IRR to 30% and the payback falls to three years.
Ivanhoe Electric: share price, chart and news
Santa Cruz 2026 study, base case
- $1.5bn after-tax NPV at 8%, copper at $4.75/lb
- $1.43bn initial capital cost
- 75,000 t a year of cathode in the first 15 years
| Case | Copper price | After-tax NPV (8%) | After-tax IRR | Payback |
|---|---|---|---|---|
| Base | $4.75/lb | $1.5bn | 19% | 4.8 years |
| Spot (21 Sept) | $6.79/lb | $3.5bn | 30% | 3 years |

Costs have risen since the 2025 study
The new study raises overall copper production compared with the 2025 version, but costs are higher too. The company blamed higher initial capital on material and labour inflation and on mine development, including ventilation shafts and tunnel access. Operating costs rose with consumables, power, labour, extra paste binder and more sustaining mine development.
Over the life of the mine, the study puts C1 cash costs at $1.47 a pound and all-in sustaining costs at $2.28 a pound. Capital intensity over the first 15 years works out at $19,100 per tonne of annual copper output. The average grade over the mine life is 1.08% copper, with modelled recovery of 92.3%. Acid use is low at about 9kg per tonne of ore, which the company puts down to the high natural chloride content of the ore.
The mine plan includes only probable reserves in the Santa Cruz and East Ridge deposits. The company reports a further 1.44 million tonnes of contained copper in indicated resources outside the reserves, and 3.33 million tonnes in inferred resources, which are excluded from the economics.
From study to construction
Access to the deposit would be through a decline about 4km long and 9.3m in diameter, cut by a tunnel boring machine the company decided to buy in May. Ivanhoe Electric says it holds all the city, county and state permits it needs for surface construction, the box cut and the start of the decline. Box cut work is expected to begin in October and tunnelling in the summer of 2027.
The project sits on nearly 6,000 acres of private land that the company fully owns, with surface, mineral and water rights, near Casa Grande, about 40 miles south of Phoenix.
"We are currently transitioning into early construction," said chief executive Taylor Melvin.
Paying for it
The $1.43bn capital bill is far larger than the company's cash, which stood at $256.9m at the end of June according to its latest quarterly filing. On 24 August, Ivanhoe Electric received a preliminary project letter from the Export-Import Bank of the United States for potential debt financing of up to $1.1bn. The letter is not a financing commitment, and the company expects final consideration by the bank's board in spring 2027. It says it is also in advanced talks on other financing options, without giving terms.
That leaves the usual risks of a company building its first mine: securing the full financing, possible dilution if equity is raised, further cost inflation, and the technical risk of tunnelling and of the heap-leach process at scale. Ivanhoe Electric does not yet generate revenue from copper.
The shares closed at $10.74 on 22 September, ahead of the release.
What to watch
- The NI 43-101 technical report, due within 45 days of the study
- The start of box cut development, expected in October 2026
- A final decision by the US EXIM board on debt financing, expected in spring 2027
- Tunnel boring from the summer of 2027, and first cathode in 2029
Sources
- Ivanhoe Electric: 2026 Preliminary Feasibility Study for the Santa Cruz Copper Project in Arizona (23 September 2026)
- Ivanhoe Electric: Preliminary Project Letter from the Export-Import Bank of the United States (24 August 2026)
- Ivanhoe Electric: Form 10-Q for the quarter ended 30 June 2026 (7 August 2026)
- Yahoo Finance: Ivanhoe Electric (IE) price history