Sunrise Energy Metals has approved construction of its Syerston scandium project in New South Wales. The company is targeting first production in the second half of 2028 and an initial 60 tonnes a year of high-purity scandium oxide, backed by a conditional US government loan offer.
The decision
Sunrise, which is listed on the ASX as SRL and trades in the US on the OTCQX as SREMF, announced on 2 November that its board had taken a final investment decision (FID) on Syerston. The company describes the project as potentially the world's first major source of scandium from primary mine supply. The company says the use of scandium has been held back by a lack of reliable, scalable supply.
Chairman Robert Friedland said the decision "reflects the Board's confidence in the quality of the Syerston resource". The company argues that scandium supply to key western markets has all but stopped since China imposed export controls on critical minerals in 2025.
Syerston at FID
- 60 tonnes a year of scandium oxide, above 99.9% purity
- US$322m central estimate of development capital
- 32 years of operating life
Sunrise Energy Metals: share price, chart and news

What will be built
Syerston lies near Fifield in central-west New South Wales. The plan is to mine 64,000 tonnes of ore a year by conventional open pit, using excavators and trucks, and to extract scandium through hydrometallurgical leaching followed by refining. The ore averages 690 parts per million of scandium in the first decade and 656 ppm over the life of the mine, with a planned recovery of 88%.
Mining is planned for 21 years, followed by 11 years of processing stockpiled ore. Construction and commissioning are expected to take 24 months. The US$322 million capital figure, set at an exchange rate of US$0.70 to the Australian dollar, covers the mine and refinery only. It excludes a possible metallisation plant, which is at scoping study stage.
Early works have started. The company broke ground on the project's water pipeline on 9 October 2026, has advanced tenders for long-lead equipment, and published a photograph of autoclave construction as at 30 September.
How it will be paid for
The FID rests on a conditional commitment of up to US$400 million of long-term debt from the US Department of War's Office of Strategic Capital (OSC), which Sunrise announced on 10 August 2026. The company also had A$148.1 million of available cash at 30 September 2026.
Sunrise is also moving its corporate home. On 2 October it signed a scheme implementation deed with Sunrise Energy Metals, Inc., a new Delaware company that would become the group's parent and list on Nasdaq. Sunrise says the move is consistent with the OSC loan offer. A scheme booklet with an independent expert's report and the details of a shareholder vote is due to be sent to shareholders shortly.
The company is also studying a larger plant to meet expected growth in demand from solid oxide fuel cells, aerospace and defence, and semiconductors. It has not decided the timing or size of any expansion, which it says will depend on customer commitments, demand, engineering, financing and board approval.
Risks and what to watch
What to watch
- The scheme booklet, the shareholder vote and court approval for the move to a US parent and a Nasdaq listing
- Final terms of the OSC loan, which is still conditional
- Construction progress against the 24-month schedule and the US$322 million estimate
- First production, targeted for the second half of 2028
The risks are typical of a first-of-its-kind mine. The loan is not yet final, and if costs run over or financing falls short, the company may need more equity, diluting shareholders. The scandium market is small and prices are not openly quoted, and the announcement did not set out sales contracts or prices. Building a new process plant also carries the risk of delays and a slower start-up than planned. Chinese policy on scandium exports could change, which would affect the supply gap Sunrise is targeting.