Vizsla Silver has pushed back first silver at its Panuco project in Mexico by a full year, to the second half of 2028 from the second half of 2027. The developer said on Thursday 19 November that it is preparing a phased return to its Sinaloa site under tighter security, almost ten months after ten colleagues were taken from the project. It has still not decided to build the mine, and the US$1.8bn after-tax value in its 2025 feasibility study has not been updated for the delay.
Panuco in three numbers
- H2 2028 new target for first silver, a year later than before
- 85% of the process plant equipment currently planned has been ordered
- US$5m initial pledge to a new Vizsla Foundation for communities in Sinaloa
Why Vizsla Silver moved the Panuco start date
The company said the new schedule reflects its current expectations for permitting, site readiness and construction timing. The delay follows the worst year in its history. On 28 January Vizsla reported that ten people had been taken from its project site at Concordia, and suspended some work at and near the site. On 6 April it confirmed that nine of those colleagues had been found dead. One is still missing.
In April the company said it would advance detailed design, construction planning and equipment buying off-site while it drew up long-term security plans, and that key work was still in line with its earlier timelines. Thursday's update is where that timeline gave way.
"We are well positioned to move into the next phase of development, with safety guiding our preparations for a phased return to site and first silver production now anticipated in the second half of 2028," said Michael Konnert, president and chief executive.
Vizsla Silver: share price, chart and news

How the phased return to the Sinaloa site will work
Vizsla said it is working with Mexican federal authorities and outside security advisers to add security infrastructure, strengthen its overall measures and bolster support on site. The timing and scope of any formal return will depend on its own assessment of security conditions and readiness, the company said.
Konnert said the progress had come "during an exceptionally difficult year" and that the company continues to support the Mexican authorities in their investigation. "We stand by the families of our colleagues and share their grief in this profound loss, as well as their need for answers," he said.
Since February the company has also been working to set up the Vizsla Foundation. It has committed an initial US$5m and plans to direct a percentage of future profits to it. The aim is long-term support for education, health and economic development in the communities around Panuco, alongside the direct help the company says it still gives affected families.
What Vizsla has designed and ordered so far
Off-site work has carried on. M3 Engineering & Technology, picked in April to run engineering, procurement and construction management, has finished about 50% of the engineering. Around 85% of the process plant equipment currently planned has been ordered. In June Vizsla chose FLSmidth as its equipment supplier, in a deal covering eight major packages from crushing and grinding through to the refining circuit.
That makes three key contracts so far: construction management, mine design and equipment supply. The main mining contract has yet to be awarded and will follow "in due course", the company said. The project's history and risks are set out in our investor profile of Vizsla Silver, published last week.
What the Panuco feasibility study says, and what it leaves out
Apart from the date, Vizsla left every figure from its November 2025 feasibility study untouched. A feasibility study is the detailed engineering and cost report a miner uses to show a project can make money. The headline numbers:
| Parameter | 2025 feasibility study |
|---|---|
| Plant size | 3,300 tonnes a day, rising to 4,000 in Year 4 |
| Average annual output | 17.4m ounces silver equivalent |
| Initial mine life | 9.4 years |
| Initial capital | US$238.7m |
| All-in sustaining cost | US$10.61 an ounce silver equivalent |
| After-tax NPV (5%) | US$1.8bn |
| After-tax IRR | 111% |
Those figures assume silver at US$35.50 an ounce and gold at US$3,100. The all-in sustaining cost is what each ounce costs to produce once the spending needed to keep the mine running is included. The net present value, or NPV, is today's value of all the cash the mine is expected to make, discounted at 5% a year. Pushing that cash a year further out lowers the figure, all else being equal.
The new schedule "does not represent an updated economic study", it said, and the economics have not been adjusted for the later start, possible cost escalation or financing costs. Metal prices matter too, and they have been falling, with silver hitting a yearly low on Wednesday.
What Vizsla Silver still has to decide
Vizsla has not made a production decision and said construction will only be approved once detailed engineering is complete and reviewed, financing is arranged and every required permit is in hand. Some funding is lined up: in May it announced a MXN$173m, roughly US$10m, working capital facility from FIFOMI, a Mexican government-backed lender to the mining industry.
The shares last traded at C$4.26 on the TSX, according to The Deep Dive. Site work was still suspended when Vizsla reported its quarterly results in September. For readers following development-stage mining stocks, the next markers at Panuco are the return to site, the mining contract and, in time, the decision to build.
When will Vizsla Silver start production at Panuco?
Vizsla Silver now targets first silver at Panuco in the second half of 2028, it said on 19 November 2026. The previous target was the second half of 2027, and the company has not yet decided to build the mine.
What happened at Vizsla Silver's Panuco site in January 2026?
On 28 January 2026 Vizsla reported that ten people had been taken from its project site at Concordia, Sinaloa. On 6 April it confirmed that nine had been found dead, with one still missing.
Is the Panuco feasibility study still valid after the delay?
On 19 November 2026 Vizsla kept the November 2025 study's figures, including a US$1.8bn after-tax NPV, but said they have not been updated for the new schedule, possible cost escalation or financing costs.
Sources
- Vizsla Silver: Vizsla Silver Provides Update on Panuco Project Development
- The Deep Dive: Vizsla Silver Delays Panuco Production Target to H2 2028 Ahead of Phased Return to Site
- Vizsla Silver: Vizsla Silver Provides an Update on Media-Reported Security Incident at the Panuco Project
- Vizsla Silver: Vizsla Silver Provides Additional Update on Situation in Concordia
- Vizsla Silver: Vizsla Silver Awards EPCM and Mine Design Contracts for the Development of the Panuco Silver-Gold Project
- Vizsla Silver: Vizsla Silver Awards Equipment Supply Agreement for Panuco
- Vizsla Silver: Vizsla Silver Secures Working Capital Facility With Mexican Government Financial Institution for Panuco