Vizsla Silver Pushes First Silver at Panuco Back a Year to 2028 as It Plans a Guarded Return

Vizsla Silver has moved first silver at its Panuco project in Mexico back a year to the second half of 2028 and is preparing a phased return to site, but has not yet decided to build the mine.

Workers in orange safety vests log rows of drill core boxes inside Vizsla Silver's core shed at Panuco, Mexico
Photo: Vizsla Silver

Vizsla Silver has pushed back first silver at its Panuco project in Mexico by a full year, to the second half of 2028 from the second half of 2027. The developer said on Thursday 19 November that it is preparing a phased return to its Sinaloa site under tighter security, almost ten months after ten colleagues were taken from the project. It has still not decided to build the mine, and the US$1.8bn after-tax value in its 2025 feasibility study has not been updated for the delay.

Panuco in three numbers

  • H2 2028 new target for first silver, a year later than before
  • 85% of the process plant equipment currently planned has been ordered
  • US$5m initial pledge to a new Vizsla Foundation for communities in Sinaloa

Why Vizsla Silver moved the Panuco start date

The company said the new schedule reflects its current expectations for permitting, site readiness and construction timing. The delay follows the worst year in its history. On 28 January Vizsla reported that ten people had been taken from its project site at Concordia, and suspended some work at and near the site. On 6 April it confirmed that nine of those colleagues had been found dead. One is still missing.

In April the company said it would advance detailed design, construction planning and equipment buying off-site while it drew up long-term security plans, and that key work was still in line with its earlier timelines. Thursday's update is where that timeline gave way.

"We are well positioned to move into the next phase of development, with safety guiding our preparations for a phased return to site and first silver production now anticipated in the second half of 2028," said Michael Konnert, president and chief executive.

Vizsla Silver: share price, chart and news

A drill rig behind orange safety fencing on a cleared forest pad at the Panuco silver-gold project in Sinaloa.
A drill rig behind orange safety fencing on a cleared forest pad at the Panuco silver-gold project in Sinaloa. Photo: Vizsla Silver

How the phased return to the Sinaloa site will work

Vizsla said it is working with Mexican federal authorities and outside security advisers to add security infrastructure, strengthen its overall measures and bolster support on site. The timing and scope of any formal return will depend on its own assessment of security conditions and readiness, the company said.

Konnert said the progress had come "during an exceptionally difficult year" and that the company continues to support the Mexican authorities in their investigation. "We stand by the families of our colleagues and share their grief in this profound loss, as well as their need for answers," he said.

Since February the company has also been working to set up the Vizsla Foundation. It has committed an initial US$5m and plans to direct a percentage of future profits to it. The aim is long-term support for education, health and economic development in the communities around Panuco, alongside the direct help the company says it still gives affected families.

What Vizsla has designed and ordered so far

Off-site work has carried on. M3 Engineering & Technology, picked in April to run engineering, procurement and construction management, has finished about 50% of the engineering. Around 85% of the process plant equipment currently planned has been ordered. In June Vizsla chose FLSmidth as its equipment supplier, in a deal covering eight major packages from crushing and grinding through to the refining circuit.

That makes three key contracts so far: construction management, mine design and equipment supply. The main mining contract has yet to be awarded and will follow "in due course", the company said. The project's history and risks are set out in our investor profile of Vizsla Silver, published last week.

What the Panuco feasibility study says, and what it leaves out

Apart from the date, Vizsla left every figure from its November 2025 feasibility study untouched. A feasibility study is the detailed engineering and cost report a miner uses to show a project can make money. The headline numbers:

Parameter2025 feasibility study
Plant size3,300 tonnes a day, rising to 4,000 in Year 4
Average annual output17.4m ounces silver equivalent
Initial mine life9.4 years
Initial capitalUS$238.7m
All-in sustaining costUS$10.61 an ounce silver equivalent
After-tax NPV (5%)US$1.8bn
After-tax IRR111%

Those figures assume silver at US$35.50 an ounce and gold at US$3,100. The all-in sustaining cost is what each ounce costs to produce once the spending needed to keep the mine running is included. The net present value, or NPV, is today's value of all the cash the mine is expected to make, discounted at 5% a year. Pushing that cash a year further out lowers the figure, all else being equal.

The new schedule "does not represent an updated economic study", it said, and the economics have not been adjusted for the later start, possible cost escalation or financing costs. Metal prices matter too, and they have been falling, with silver hitting a yearly low on Wednesday.

What Vizsla Silver still has to decide

Vizsla has not made a production decision and said construction will only be approved once detailed engineering is complete and reviewed, financing is arranged and every required permit is in hand. Some funding is lined up: in May it announced a MXN$173m, roughly US$10m, working capital facility from FIFOMI, a Mexican government-backed lender to the mining industry.

The shares last traded at C$4.26 on the TSX, according to The Deep Dive. Site work was still suspended when Vizsla reported its quarterly results in September. For readers following development-stage mining stocks, the next markers at Panuco are the return to site, the mining contract and, in time, the decision to build.

When will Vizsla Silver start production at Panuco?

Vizsla Silver now targets first silver at Panuco in the second half of 2028, it said on 19 November 2026. The previous target was the second half of 2027, and the company has not yet decided to build the mine.

What happened at Vizsla Silver's Panuco site in January 2026?

On 28 January 2026 Vizsla reported that ten people had been taken from its project site at Concordia, Sinaloa. On 6 April it confirmed that nine had been found dead, with one still missing.

Is the Panuco feasibility study still valid after the delay?

On 19 November 2026 Vizsla kept the November 2025 study's figures, including a US$1.8bn after-tax NPV, but said they have not been updated for the new schedule, possible cost escalation or financing costs.

Sources

Related stories

Staff in orange safety vests logging drill core laid out in labelled core boxes inside the core shed at Vizsla Silver's Panuco project.
Investing

Vizsla Silver Investor Profile: Panuco, a US$400m Cash Pile and a Paused Site

Vizsla Silver is developing the Panuco silver-gold project in Mexico with US$406m of cash and a 2027 production target, while site work stays paused after January's deadly security…

A drill rig under red shade canopies on a wooded hillside, with a worker in a safety vest beside it, from Vizsla Silver's website.
Markets

Vizsla Silver Holds US$406m of Cash as Panuco Site Work Stays Suspended

Vizsla Silver ended its July quarter with US$406.5m of cash and a US$19.8m net loss, while site work at its Panuco silver-gold project in Mexico stays suspended after January's…

Line chart of Endeavour Silver daily closing prices in the three months to 21 November 2026
Investing

Endeavour Silver's US$736m Pitarrilla Plan Assumes US$50 Silver. Spot Closed the Week at US$41

Endeavour Silver's Pitarrilla feasibility study values the Mexican mine at US$736m after tax at US$50 silver; at US$40 that falls to US$423m, against a US$585m build cost.

Aerial view of the Zgounder processing plant in Morocco, with tanks, conveyors and the Aya Gold & Silver logo on a shed roof, mountains behind
Investing

Aya Gold & Silver Corrects Q3 Cash Costs to $14.28 an Ounce After Silver Double Count

Aya Gold & Silver refiled its Q3 MD&A after silver in transit was deducted twice. Zgounder ounces sold rise to 1,392,478 and cash costs fall to $14.28 from $15.51. Revenue and…

AMD's headquarters building at 2485 Augustine Drive in Santa Clara, California, photographed in March 2024
Investing

AMD Sheds 20.5% in a Week as a Short Seller Finds Its Code at a Blacklisted Chinese Firm

AMD shares fell 20.5% in a week to $424.39 after short seller Hunterbrook said AMD firmware kept reaching blacklisted Chinese server maker IEIT. AMD says the claims misrepresent…

Dell's glass-fronted headquarters building with the round Dell logo in Round Rock, Texas, in June 2015
Investing

Dell's $95bn AI Backlog Faces Thanksgiving Week's Big Test After a 42% Share Slide

Dell reports on Tuesday 24 November with a record $95bn AI server backlog after a 42% share slide, leading a Thanksgiving week of results from HPE, Medtronic, Workday, HP and…

Aerial view of a historical open-pit working beside a creek and gravel road on TDG Gold's Shasta property in north-central British Columbia
Investing

TDG Gold's C$1.18bn Shasta Study Assumes US$50 Silver, and Silver Just Closed at US$41

TDG Gold's first Shasta PEA shows a C$1.18bn after-tax NPV and a C$604.9m build cost, but it assumes US$50 silver, far above Friday's US$41.08 close, and leans on Inferred tonnes.

The old Toronto Stock Exchange building's stone facade on Bay Street, set into a dark glass tower
Investing

Copper's Slide to $12,765 Undercuts Lundin's Summer Price by 15% as Miners' Costs Rise

Copper fell as low as US$12,765 a tonne on 18 November, about 15% below the US$6.85/lb Lundin Mining realised in Q3, while First Quantum and Ero Copper raised their 2026 cost…