TDG Gold's first Shasta PEA shows a C$1.18bn after-tax NPV and a C$604.9m build cost, but it assumes US$50 silver, far above Friday's US$41.08 close, and leans on Inferred tonnes.

Aerial view of a historical open-pit working beside a creek and gravel road on TDG Gold's Shasta property in north-central British Columbia
Photo: TDG Gold

TDG Gold's first economic study of its Shasta gold and silver project in British Columbia values a 9.9-year open-pit mine at C$1.18bn after tax, but it assumes silver at US$50 an ounce, and silver closed the week at US$41.08. The mine would cost C$604.9m to build, more than five times the C$110m the TSX Venture company expects from selling a stake in a neighbouring property, and most of the resource tonnes sit in the least certain Inferred category.

Shasta PEA in three numbers

  • C$1.18bn after-tax NPV at a 5% discount rate, at US$3,550 gold and US$50 silver
  • C$604.9m initial capital, with an accuracy range of 30% below to 50% above
  • US$41.08 Friday's silver close, 18% below the study's price

What TDG Gold's Shasta study says

TDG Gold published the preliminary economic assessment, or PEA, on Tuesday 17 November. A PEA is the first and roughest study on the road to a mine. This one joins Shasta with the much smaller, higher-grade Mets deposit, both in the Toodoggone district of north-central British Columbia.

Two open pits would feed one mill of 4m tonnes a year, producing about 71,200 ounces of gold and 2.82m ounces of silver a year for 9.9 years. All-in sustaining costs, the running cost per ounce including upkeep, are put at US$1,283 per gold-equivalent ounce. Payback is 1.8 years from first production and the after-tax internal rate of return is 38.8%.

"The PEA defines what we can evaluate economically today," Paul Geddes, TDG's senior vice-president of business development and strategy, said in the release.

Geologist's rock hammer resting on a dark boulder crossed by white quartz veins at TDG Gold's Shasta property.
Geologist's rock hammer resting on a dark boulder crossed by white quartz veins at TDG Gold's Shasta property. Photo: TDG Gold

Why the silver price matters more than gold for Shasta

Gold closed on Friday at US$3,525.75, according to Investing News Network, within 1% of the study's US$3,550 even after gold's slide to its lowest since September 2025. Silver is the problem. It fell 18% in the week to US$41.08, and it supplies about 36% of Shasta's life-of-mine revenue at base-case prices.

The company's sensitivity table moves both metals together:

CaseGold (US$/oz)Silver (US$/oz)After-tax NPVIRR
Base case3,55050C$1.18bn38.8%
Prices 10% lower3,19545C$942m33.0%
Prices 20% lower2,84040C$703m26.7%

On a straight-line BMK News reading of that table, Friday's prices cut revenue by about 7%, pointing to an NPV nearer C$1.0bn. The release also converts silver into gold-equivalent ounces at 71 to 1; on Friday the ratio was about 86 to 1. On our arithmetic that trims annual output to about 104,000 gold-equivalent ounces and lifts the cost per ounce to roughly US$1,370. That is why silver's slide to a yearly low hurts Shasta more than the gold price suggests.

How much of the Shasta resource is Inferred

The new resource has 17.12m tonnes Indicated and 27.37m tonnes Inferred across Shasta and Mets, so about 62% of the tonnes are Inferred, material the release calls "too speculative geologically" to become reserves. The plan schedules 38.21m tonnes of mill feed, more than twice the Indicated tonnage, and the release does not say how much of that feed is Inferred.

No new drilling has gone in since the December 2024 estimate. The company says higher metal price assumptions lowered the cut-off grade and enlarged the conceptual pit, adding lower-grade tonnes. Higher prices made the deposit bigger on paper; lower prices work in reverse.

How TDG Gold could pay for a C$605m mine

TDG had 281.3m shares in issue on 20 October and 305.6m fully diluted, counting 18.7m options and 5.6m warrants, according to its capital structure page. Its main source of new money is the deal it signed on Thursday 12 November to sell 51% of its Aurora West property to Freeport-McMoRan for C$110m in cash. Freeport can raise its stake by spending a further C$80m on exploration and paying TDG another C$40m. The sale needs TSX Venture Exchange approval, the restructuring behind it is expected in December, and Shasta stays 100% with TDG.

The C$110m covers about 18% of the build cost. The capital estimate is a Class 5 figure, accurate to between 30% below and 50% above, so the bill could reach about C$907m, all spent in the two years before production. The release itself warns that the capital figure does not necessarily represent the total outside financing needed. Koryx Copper's Haib study, priced at $5 copper, shows the same pattern this month.

The bull case and the bear case

  • Bull: even with both metals 20% lower, the NPV of C$703m is 1.2 times the initial capital.
  • Bull: a low strip ratio, conventional flotation, road access and C$110m of new cash without new shares if the Freeport deal closes.
  • Bear: silver already sits near the study's downside case, and most resource tonnes are Inferred.
  • Bear: no permit for a full mine, and a build bill more than five times the cash in prospect.

The permits Shasta still needs

The existing Mines Act permit covers about 175 hectares of historical workings, not the full project. TDG needs a provincial environmental assessment certificate, a federal impact assessment decision, an amended Mines Act permit, a discharge permit and a Fisheries Act authorisation to divert Jock Creek from year four, which the release calls a material engineering and permitting consideration. The company also says its existing relationships with First Nations do not amount to consent for the larger development.

Shares of juniors this far from production tend to swing harder than the metal, as our explainer on why gold miners fall harder than gold sets out.

What to watch next at TDG Gold

TDG says the NI 43-101 technical report will be filed on SEDAR+ within 45 days of 17 November, which points to about 1 January. Next come TSX Venture approval and the closing of the Freeport sale, then how TDG spends the money. The silver price against the study's US$50 is the number to track.

What is TDG Gold's Shasta project worth?

TDG Gold's PEA of 17 November 2026 puts Shasta's after-tax NPV at C$1.18bn at US$50 silver, or C$703m if gold and silver are both 20% lower.

How much will the Shasta mine cost to build?

Initial capital is C$604.9m, including C$92.6m of contingency, and the estimate could be 30% lower or 50% higher.

When is the TDG Gold Shasta technical report due?

TDG Gold says the NI 43-101 technical report will be filed within 45 days of 17 November 2026, by about early January 2027.

Sources

Related stories

Line chart of Endeavour Silver daily closing prices in the three months to 21 November 2026
Investing

Endeavour Silver's US$736m Pitarrilla Plan Assumes US$50 Silver. Spot Closed the Week at US$41

Endeavour Silver's Pitarrilla feasibility study values the Mexican mine at US$736m after tax at US$50 silver; at US$40 that falls to US$423m, against a US$585m build cost.

Cut drill core from Brixton hole LM-26-480 at Langis, Ontario, showing grey cobaltite and native silver in a pale vein
Investing

Brixton Metals Drilled 142,770 g/t Silver, a Claimed Record. It Was 30 Centimetres Wide

Brixton Metals reported 142,770 g/t silver over just 0.30 m at Langis, Ontario, and 5 m at 704 g/t in a follow-up hole. Grade times width, true width and depth show what such…

Workers in orange safety vests log rows of drill core boxes inside Vizsla Silver's core shed at Panuco, Mexico
Investing

Vizsla Silver Pushes First Silver at Panuco Back a Year to 2028 as It Plans a Guarded Return

Vizsla Silver has moved first silver at its Panuco project in Mexico back a year to the second half of 2028 and is preparing a phased return to site, but has not yet decided to…

Aerial view of the Zgounder processing plant in Morocco, with tanks, conveyors and the Aya Gold & Silver logo on a shed roof, mountains behind
Investing

Aya Gold & Silver Corrects Q3 Cash Costs to $14.28 an Ounce After Silver Double Count

Aya Gold & Silver refiled its Q3 MD&A after silver in transit was deducted twice. Zgounder ounces sold rise to 1,392,478 and cash costs fall to $14.28 from $15.51. Revenue and…

AMD's headquarters building at 2485 Augustine Drive in Santa Clara, California, photographed in March 2024
Investing

AMD Sheds 20.5% in a Week as a Short Seller Finds Its Code at a Blacklisted Chinese Firm

AMD shares fell 20.5% in a week to $424.39 after short seller Hunterbrook said AMD firmware kept reaching blacklisted Chinese server maker IEIT. AMD says the claims misrepresent…

Dell's glass-fronted headquarters building with the round Dell logo in Round Rock, Texas, in June 2015
Investing

Dell's $95bn AI Backlog Faces Thanksgiving Week's Big Test After a 42% Share Slide

Dell reports on Tuesday 24 November with a record $95bn AI server backlog after a 42% share slide, leading a Thanksgiving week of results from HPE, Medtronic, Workday, HP and…

The old Toronto Stock Exchange building's stone facade on Bay Street, set into a dark glass tower
Investing

Copper's Slide to $12,765 Undercuts Lundin's Summer Price by 15% as Miners' Costs Rise

Copper fell as low as US$12,765 a tonne on 18 November, about 15% below the US$6.85/lb Lundin Mining realised in Q3, while First Quantum and Ero Copper raised their 2026 cost…

Aerial view of an exploration tent camp in pine forest beside a lake at Skyharbour's Russell Lake uranium project, Saskatchewan
Investing

Skyharbour Pays a Marketer US$150,000 Up Front as the TSX Venture Sinks 14.7% in a Week

Skyharbour Resources is paying US$150,000 up front for a 12-month investor campaign, while Alset AI will spend C$200,000 on social media, 30.7% of the C$651,500 it just raised.