Snowline Gold said on Wednesday 18 November that hole V-26-165 at its Valley deposit in Yukon returned 450.2 m at 1.47 grams of gold per tonne from surface, beating the resource model at that spot. Twelve kilometres away, its Duke target cut 65.8 m at 1.03 g/t, widening what the company calls a new gold discovery on its Rogue project. The results land with gold near its lowest in more than a year, and the new Valley holes will not feed into the study due in early 2027.
Snowline's latest drill results
- 450.2 m at 1.47 g/t gold from surface in Valley hole V-26-165, or 1.36 g/t with high grades capped
- 65.8 m at 1.03 g/t gold at Duke in hole DUK-26-004, or 0.70 g/t capped
- Q1 2027 target for the Valley pre-feasibility study, which leaves these holes out
What Snowline Gold found at the Duke target
Duke sits on Rogue, the project Snowline owns outright in eastern Yukon, 12 km south-east of Valley. At its heart is an intrusion, a body of once-molten rock about 1.4 km by 1.3 km, cut by breccias: shattered rock cemented back together by later fluids, which can carry gold.
Hole DUK-26-004 hit 65.8 m averaging 1.03 g/t gold from 230.0 m down the hole, including a single metre at 32.2 g/t. Core loggers flagged several spots of visible gold. A second hole, 675 m to the north-east, returned 54.5 m at 0.41 g/t.
Like Valley, Duke is a reduced-intrusion related gold system (RIRGS), where the gold is tied to an intrusion, but here it sits in breccia pipes. "Drilling at Duke confirms a new style of RIRGS gold mineralization on the Rogue Project, with intrusion hosted breccia pipes returning some of the strongest numbers we have seen in drilling at Rogue outside of Valley," said chief executive Scott Berdahl.
The mineralised zone in DUK-26-004 is wider than anything seen at surface, which Snowline says suggests a hidden system that may be open at depth. Full assays from one of this year's five Duke holes are still pending.
Snowline Gold: share price, chart and news

Why the capped grades matter for Duke and Valley
Capping cuts any sample richer than a set ceiling, here 10 g/t, down to that ceiling before averaging, so one lucky metre cannot flatter a long interval. On that test the two targets part ways. Duke's 1.03 g/t falls to 0.70 g/t, and the 64.8 m outside the 32.2 g/t metre average 0.55 g/t. Valley holds up far better: 1.47 g/t becomes 1.36 g/t. All lengths are measured down the hole; true widths have not been determined.
| Hole | Interval | Grade (g/t gold) | Capped at 10 g/t |
|---|---|---|---|
| V-26-165 (Valley) | 450.2 m from 5.8 m | 1.47 | 1.36 |
| including | 210.5 m from 95.0 m | 2.07 | 1.84 |
| DUK-26-004 (Duke) | 65.8 m from 230.0 m | 1.03 | 0.70 |
How Valley hole V-26-165 compares with the resource
V-26-165 was an infill hole, drilled between earlier holes to firm up known ground. Valley holds 7.94 million ounces in the measured and indicated categories at an average of 1.21 g/t, plus 0.89 million ounces inferred at 0.62 g/t, according to the company.
Inside the planned pit, Snowline said, the hole beat the grades predicted by the block model behind the resource by more than 20%. It then ended in a separate zone of 44.3 m at 0.72 g/t, north-east of the deposit in ground the company has yet to test properly, much as the deepest Valley hole in September found gold well below the pit.
Why the new holes will not be in the pre-feasibility study
A pre-feasibility study is the detailed engineering and cost study that follows a preliminary economic assessment, which Valley received in 2025. Snowline said its study remains on track for the first quarter of 2027, alongside a project description to start formal permitting.
The 2026 Valley holes "will not be incorporated" into it, Berdahl said; they will inform later resource estimates and studies. A profile of the Valley gold project sets out the resource, the cash and the timetable.
What the gold price fall means for Snowline Gold
Gold fell to about $3,770 an ounce on Wednesday morning, its lowest in more than a year according to the World Gold Council, and roughly 31% below its January peak of about $5,500, Ecofin Agency reported. Early on Thursday 19 November, European time, Kitco quoted spot gold at $3,725.50 after a session low of $3,693.10, extending Wednesday's fall below $3,800.
An explorer sells no gold, but its shares price the ounces in the ground, and gold miners tend to fall harder than gold when the metal turns. Snowline closed at C$12.37 on Tuesday, before the release, down 0.96%, according to Mugglehead.
At that price, a tonne of rock at Valley's 1.21 g/t average holds about $145 of gold, before mining and processing costs. At the capped 1.36 g/t of V-26-165 it is about $163; at Duke's capped 0.70 g/t, about $84. More gold per tonne leaves more room for costs when prices fall.
Duke is still a handful of holes, not a resource, and Snowline plans to follow up its 2026 targets in 2027. The last Duke assays and the study in the first quarter are the next markers.
What did Snowline Gold announce on 18 November 2026?
On Wednesday 18 November 2026 Snowline Gold reported 450.2 m at 1.47 g/t gold from surface in Valley hole V-26-165 in Yukon, and 65.8 m at 1.03 g/t at its Duke target.
Will the new Valley drill results be in Snowline's pre-feasibility study?
No. Snowline said on 18 November 2026 that its 2026 Valley holes will not be in the pre-feasibility study due in the first quarter of 2027.
Sources
- Snowline Gold: Snowline Expands New Gold Discovery at Its Duke Target, Intersecting 1.03 Grams per Tonne Gold Over 65.8 m, and Reports 1.47 Grams per Tonne Gold Over 450.2 m From Surface at Valley
- Mugglehead: Snowline Gold reports 450.2 metres at 1.47 g/t at Valley
- The Deep Dive: Snowline Gold Hits 65.8 Metres of 1.03 G/T Gold at New Duke Target
- Ecofin Agency: Gold Falls to Lowest in More Than a Year as Fed Rate Bets Build
- Kitco: Gold Price Today: Price of Gold Per Ounce, 24 Hour Spot Chart